Tampa, FL Hurricane Preparedness: Flood Elevation (2026)
Key Facts
- Checkpoint
- Placement of lowest floor, incl. basement
- Required before
- Any further vertical construction
- Referenced codes
- FBC Building §1612.4 & Residential R322
- Who certifies
- Florida-licensed surveyor
- Citation
- City Code Sec. 5-110.3.3
Summary
Before framing can rise above the slab, Tampa requires an elevation certification for the lowest floor of any new building in a flood hazard area. City Code Sec. 5-110.3.3 ties this hurricane-season safeguard to Florida Building Code Sections 1612.4 and R322, and the building official won't approve further vertical construction without it.
5-110.3.3. Lowest floor elevation. In flood hazard areas, upon placement of the lowest floor, including the basement, and prior to further vertical construction, the elevation certification required in Section 1612.4 of the Florida Building Code, Building and Section R322 of the Florida Building Code, Residential, shall be submitted to the building official.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 148).
Full Breakdown
Section 5-110.3.3, part of the required-inspections article adopted by Ord. No. 2024-15, sets a hard checkpoint in the construction sequence for any site in a mapped flood hazard area: once the lowest floor, including a basement, if any, is placed, and before any further vertical construction proceeds, the contractor or owner must submit the elevation certification required under Section 1612.4 of the Florida Building Code, Building, and Section R322 of the Florida Building Code, Residential, to the building official. This dovetails with Sec. 5-110.3's foundation-inspection checklist, which separately requires that a copy of the under-construction flood certificate of elevation, or a surveyor-certified survey establishing the lowest floor, be available for review at the job site before going vertical for new construction in an 'A' or 'V' flood zone.
In practice, a Florida-licensed surveyor documents the as-built elevation of the lowest floor relative to the flood hazard map datum (NAVD 88, per Sec. 5-121.81) before framing continues, giving the city, and later FEMA and the owner's flood insurer, a verified record that the structure was actually built to the design flood elevation rather than merely permitted to it. A final certification of the lowest floor elevation is required again at the final inspection stage under the related Sec. 5-121.104/.105 provisions for structures exempt from the Florida Building Code.
Because this checkpoint sits inside the standard building-permit inspection sequence, missing it stops the job: inspectors will not release the framing inspection, and the project cannot proceed to a certificate of occupancy, until the elevation documentation is on file.
Violations & Fines
Framing and subsequent inspections are withheld until the lowest-floor elevation certification is filed; a project that proceeds vertically without it is treated as an inspection failure under Sec. 5-110.1, and the building official can require exposed work to be uncovered for verification, at the owner's expense, before signing off.
Frequently Asked Questions
When during construction must the elevation certificate be filed?
Who prepares the certification?
What happens if a builder skips this step?
Sources & Official References
Other rules in Tampa
Florida rules heatmap·Compare Tampa to another location·View the Florida hurricane preparedness overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.