Buncombe County, NC Landscaping Rules: Rainwater Harvesting (2026)
Key Facts
- Governing section
- Sec. 78-650(c)(1)a, Environment/Transit table
- Points available
- 5 of up to 250% bonus
- Approval needed
- County stormwater management engineer review
- Applies to
- Community Oriented Developments only
- Maintenance duty
- Recorded in perpetuity per Sec. 78-650(c)(6)b.4
Summary
Buncombe County does not require rainwater harvesting, but its zoning code rewards it. A Community Oriented Development can earn 5 of up to 250 percent bonus density points by installing a rainwater or greywater cistern system, subject to county stormwater engineer sign-off.
Rainwater/greywater collection 5 points for water collection systems Development incorporates the installation of either rainwater or greywater collection systems through the use of cistern reservoirs subject to review and approval of the county stormwater management engineer 5
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 37).
Full Breakdown
The county's Community Oriented Development (COD) provisions in Sec. 78-650 let a residential project increase its allowed density up to 250 percent above the base district density in Sec. 78-642, but only by earning points across a table of Community, Environment/Transit and Economy criteria. " That review, not a separate rainwater-specific permit, is the operative check: the engineer confirms the cistern system before the points count toward the density bonus. Points from rainwater/greywater collection can be combined with other Environment/Transit items such as riparian buffer conservation (15-25 points), low-impact development BMPs (5 points each) and open space preservation (5 points per acre), but a COD applicant must draw points from at least two of the three principal categories to qualify for any bonus at all, so a single cistern system alone will not unlock density.
Beyond the density calculation, Sec. 4 also requires the deed restrictions recorded for an approved COD to include maintenance language covering "rainwater collection/greywater harvesting" alongside other point-earning improvements, so a system installed to earn points must be kept functioning for the life of the development, not just at the time of approval. This is strictly a residential-development incentive: single-family homeowners outside a COD are not regulated, required, or credited for installing a rain barrel or cistern.
Violations & Fines
There is no separate rainwater-harvesting violation because there is no separate mandate; the exposure runs through the COD approval itself. If a recorded COD's deed restrictions fail to maintain the rainwater/greywater system that earned density points, that is treated as a failure to comply with the recorded plan and deed restrictions approved under Sec. 78-650(c)(6), which the planning department enforces against the density approval, not as a stand-alone fine.
Frequently Asked Questions
Does Buncombe County require homeowners to harvest rainwater?
How many density points does a rainwater system earn?
Who signs off on a cistern system used for the density bonus?
Sources & Official References
Other rules in Buncombe County
Compare Buncombe County to another location·View the North Carolina landscaping rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.