Pierce County, WA Parking Rules: EV Charging (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified July 2026

Key Facts

EV Code
PCC 18A.35.040(9)
Circuit Requirement
40-amp 208/240-volt
Accessible EV Stations
10% of accessible spaces
Small-Lot Exception
Under 10 spaces
Standards
RCW 19.28, NEC Article 625

Summary

Pierce County requires new development in unincorporated areas to provide electric vehicle charging infrastructure under PCC 18A.35.040, following Table 18A.35.040-3 for EV charging stations, EV-Ready, and EV-Capable spaces. Equipment must meet RCW Chapter 19.28 and NEC Article 625, with exceptions for small parking areas and sites without power.

City-specific rules exist: Lakewood has its own ev charging rules that differ from Pierce County's county-level regulations. If you live in Lakewood, check the city-specific page instead.

Buildings and accessory structures shall be provided with EV charging stations, EV-Ready parking spaces, and EV-capable parking spaces in accordance with Table 18A.35.040-3. Calculations shall be rounded up to the nearest whole number.

View official code

Official source re-checked September 8, 2026: no newer edition of the code had been published (publisher’s edition: current through Ordinance 2026-515, and legislation passed through May 26, 2026).

Full Breakdown

Under the Title 18A zoning parking code, new buildings and accessory structures in unincorporated Pierce County must provide EV charging stations, EV-Ready parking spaces, and EV-Capable parking spaces according to Table 18A.35.040-3, with calculations rounded up to the nearest whole number. EV supply equipment must be installed per Chapter 19.28 RCW and the National Electrical Code, Article 625. Each EV-Ready space and EV charging station requires a minimum 40-ampere dedicated 208/240-volt branch circuit, and EV-Capable spaces require a listed raceway sized for the same circuit. Ten percent of accessible parking spaces must be EV charging stations, with an additional ten percent EV-Ready.

Violations & Fines

Failing to install the required EV charging stations, EV-Ready, or EV-Capable spaces and circuits for new construction under PCC 18A.35.040 and Table 18A.35.040-3 is a zoning violation that can block permit approval.

Frequently Asked Questions

Does new development in Pierce County need EV charging?
Yes. Under PCC 18A.35.040, new buildings and accessory structures in unincorporated Pierce County must provide EV charging stations, EV-Ready, and EV-Capable spaces per Table 18A.35.040-3, unless an exception such as the under-10-space rule applies.
What electrical capacity is required for EV spaces?
Each EV-Ready space and EV charging station needs a minimum 40-ampere dedicated 208/240-volt branch circuit, and EV-Capable spaces need a listed raceway sized for the same, per PCC 18A.35.040 and NEC Article 625.

Sources & Official References

Other rules in Pierce County

All Pierce County rules

Compare Pierce County to another location·View the Washington parking rules overview

Get notified when EV Charging in Pierce County, WA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.