Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Governing section
Zoning Ordinance Sec. 4.87(L)
Charging station trigger
1 station per development with 100+ spaces
EV-ready ratio
1:5 of new parking spaces
Wiring standard
National Electrical Code (NFPA 70)
Minimum raceway size
1 inch
Applies in
Mountain View Overlay District only

Summary

In the Mountain View Overlay District near Hartsfield-Jackson, Clayton County requires at least one EV charging station for any new development with 100 or more parking spaces, and it mandates future-ready EVSE wiring at a 1:5 ratio for new commercial and mixed-use lots under Zoning Ordinance Sec. 4.87(L).

These county ordinances apply to unincorporated areas of Clayton County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

L.Electric vehicle charging infrastructure.1.A minimum of one (1) electric vehicle charging station shall be provided for all new developments that have 100 parking spaces or more.2.All new commercial, office, industrial and mixed use developments, as regulated by the International Building Code, are required to provide EVSE infrastructure to accommodate the future installation of Electric Vehicle Supply Equipment. The infrastructure shall be provided per this section.(A)The EVSE infrastructure shall be installed per the requirements of the current edition of the National Electrical Code (NFPA 70) as adopted and amended by the State of Georgia for enforcement by Clayton County.(1)The off-road parking provided for buildings containing commercial, office, industrial and mixed use occupancies shall have EVSE infrastructure installed at the parking spaces dedicated for the use of the building.(2)The ratio of electric vehicle parking spaces to non-electrical vehicle parking spaces shall be 1:5 and only applies to the total new parking spaces.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 104).

Full Breakdown

Sec. 87, Public Improvements, of the Mountain View Overlay District requires any new development with 100 or more parking spaces to install at least one electric vehicle charging station. Beyond that trigger, subsection L goes further: every new commercial, office, industrial and mixed-use development in the overlay, regardless of size, must build out Electric Vehicle Supply Equipment (EVSE) infrastructure, meaning the raceways, panel capacity and conduit needed to support future chargers, even if the chargers themselves are not installed yet. That infrastructure has to be installed per the National Electrical Code (NFPA 70) as adopted by the State of Georgia, and the ratio of EV-ready parking spaces to standard spaces is fixed at 1:5 of the total new spaces added.

The raceway connecting the electrical panel to each future EV space must be sized under the National Electrical Code and cannot be smaller than 1 inch, must include a pull rope for future wiring, and has to be sealed and labeled for later use. ' Dual-port EVSE stalls may double as ADA-accessible spaces, but the code makes clear that accessible-parking use takes precedence over EV-charging use when the two conflict, and no EVSE placement may create a trip hazard or block an accessible path of travel.

Violations & Fines

A site plan for the Mountain View Overlay that omits the required EVSE raceways, panel capacity, or the 100-space charging-station trigger will not clear Department of Community Development site plan review, and a project cannot pass final electrical inspection without the stenciled 'FUTURE ELECTRIC VEHICLE CHARGING EQUIPMENT AND PANELS' labeling in the equipment room. Developers may seek relief through the Administrative Appeals Process of Article 13.22.

Frequently Asked Questions

Does every new building in Clayton County need EV chargers?
Only within the Mountain View Overlay District near Hartsfield-Jackson. Sec. 4.87(L) requires at least one working charging station once a development has 100 or more parking spaces, and it requires EVSE-ready wiring infrastructure in all new commercial, office, industrial and mixed-use projects in that overlay regardless of size.
What is the required ratio of EV parking spaces?
The ratio of electric vehicle parking spaces to non-electric spaces is fixed at 1:5, applied only to the total number of new parking spaces a project adds, not to existing parking that predates the requirement.
Can an EV charging space double as a disabled parking space?
Yes, a dual-port EVSE stall may serve as both an ADA-accessible space and a non-accessible EV space with ADA-compliant hardware, but Sec. 4.87(L) states the accessible-parking use takes precedence whenever the two uses conflict.

Sources & Official References

Other rules in Clayton County

All Clayton County rules

Compare Clayton County to another location·View the Georgia parking rules overview

Get notified when EV Charging in Clayton County, GA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.