Key Facts
- Default status
- Permitted use, all zone districts
- Review level
- No discretionary review by default
- Trigger for permit
- Specific adverse impact (Sec. 16.14.040)
- Fallback permit
- Use permit under Sec. 16.14.070
- Adopted by
- Ordinance No. 2026-01, Feb. 24, 2026
Summary
Electric vehicle charging stations are a by-right use in every zone district in unincorporated Shasta County, exempt from discretionary review unless a station would cause a specific adverse impact. If that threshold is met, the county requires a use permit instead of allowing outright approval.
17.88.080 - Electric vehicle charging stations. A.Electric vehicle charging stations are a permitted use in all zone districts and are not subject to discretionary review provided the following criteria is met:1.The proposed electric vehicle charging station or stations proposed would not cause a specific adverse impact as defined in Shasta County Code Section 16.14.040.B.If the above criteria are not met, the facility may be permitted if a use permit is issued pursuant to Shasta County Code Section 16.14.070 and subject to Section 17.92.020. (Ord. No. 2026-01, § II, 2-24-2026)
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code: Supplement 22).
Full Breakdown
080, adopted by Ordinance No. 2026-01 in February 2026, governs where and how electric vehicle charging stations can be installed countywide. 040, the county's expedited permitting ordinance for residential and commercial solar and EV infrastructure adopted to implement state streamlining law. That cross-reference ties the local standard to the state-defined list of adverse impacts, things like a significant, quantifiable, direct and unavoidable threat to public health and safety that cannot be feasibly mitigated. 020, which includes public hearing and Planning Commission review. In practice, this means the default posture for EV charging equipment, whether a single Level 2 charger at a home or a small commercial charging installation, is ministerial, over-the-counter approval with no environmental or design review beyond a building permit, and the more involved land-use permit track is reserved for installations that a technical adverse-impact finding actually flags as problematic.
Violations & Fines
Installing an electric vehicle charging station that meets the adverse-impact criteria under Section 16.14.040 without first securing the required use permit under Section 16.14.070 is a zoning violation enforceable through the county's standard code enforcement process, which can require removal or retrofitting of the installation until the use permit is obtained.
Frequently Asked Questions
Does a Shasta County property owner need a special permit to install an EV charger?
What happens if an EV charging station would cause a specific adverse impact?
When did Shasta County adopt its electric vehicle charging station rule?
Sources & Official References
Other rules in Shasta County