Key Facts
- Trigger
- New building, new parking facility, or capacity increase over fifty percent
- Multifamily (10 or more units) and lodging
- Five percent of parking spaces
- Office, institutional, municipal, medical
- Three percent of parking spaces
- Industrial and recreational/entertainment/cultural
- One percent of parking spaces
- Charging level required
- Level 2 or higher
- Charging stations by zone
- Allowed with a primary use in every zoning designation
Summary
In the City of Lacey, Washington, LMC 16.73.032 requires level 2 or higher electric vehicle charging stations at a set percentage of parking spaces when a new building or new off-street parking facility is developed, or when parking capacity grows by more than fifty percent. Table 16T-86 sets the percentages from five percent for multifamily and lodging down to one percent for industrial.
A. Electric vehicle charging station(s) level 2 or higher shall be provided for the land uses in Table 16T-86; provided, that one of the following occurs: 1. A new building or a new off-street parking facility is developed; 2. The parking capacity of an existing building, site, or parking facility is increased by more than fifty percent. The fifty percent threshold shall be cumulative over the most recent five years, including calculations of all previously exempt expansions. ... Table 16T-86 Required Number of Electric Vehicle Charging Stations Land Use Type Percentage of Parking Spaces* Multifamily residential, 10 or more units 5% Lodging 5% Office, institutional, municipal, medical 3% Industrial 1% Recreational/entertainment/cultural 1% *Percentage shall be rounded to the nearest whole number of spaces. ... For percentages equaling one-half space or less, no spaces are required.
Full Breakdown
LMC 16.73.032(A) requires electric vehicle charging stations, level 2 or higher, for the land uses in Table 16T-86 when one of two triggers occurs: a new building or a new off-street parking facility is developed, or the parking capacity of an existing building, site or parking facility is increased by more than fifty percent. The fifty percent threshold is cumulative over the most recent five years, including calculations of all previously exempt expansions.
Table 16T-86 sets the share of parking spaces: five percent for multifamily residential of 10 or more units, five percent for lodging, three percent for office, institutional, municipal and medical uses, and one percent each for industrial and for recreational, entertainment and cultural uses. The table's footnote rounds to the nearest whole number of spaces, and for percentages equaling one-half space or less, no spaces are required. LMC 16.73.020(D) describes level 2 charging as requiring a forty-amp to one-hundred-amp breaker on a two-hundred-forty-volt AC circuit.
LMC 16.73.030(A) treats electric vehicle charging stations as an allowed use in association with a primary permitted use in every zoning designation. Battery exchange stations are permitted in commercial, industrial or mixed use zones, are specifically prohibited in exclusively residential zones and OSI zones, and go through site plan review under Chapter 11.07 LMC (LMC 16.73.035). Under LMC 16.73.015, electric vehicle charging stations should be reserved for parking and charging electric vehicles only, and electric vehicles can park in any space designated for public parking subject to the restrictions that apply to any other vehicle. LMC 16.73.040 adds that each charging space should be posted as electric vehicle charging only, with days and hours stated if the owner enforces time limits or tow away, that the posting identify voltage and amperage levels, and that charging stations in the streetscape be approved by the public works director.
Violations & Fines
Chapter 16.73 prints no fine or penalty clause of its own. The stall percentages in Table 16T-86 apply when a new building or new off-street parking facility is developed or capacity is expanded past the fifty percent threshold. The reservation of charging stalls in LMC 16.73.015(A) and the design criteria in LMC 16.73.040 are written as should-statements and guidelines. Tow away at a charging stall is an owner-enforced provision, and signage must state days and hours when it is enforced.
Frequently Asked Questions
When must a Lacey development add EV charging stations?
What percentage of parking must be EV charging in the City of Lacey?
Can a regular car park in an EV charging space in Lacey?
Are home EV chargers allowed in Lacey?
Sources & Official References
Other rules in Lacey
Compare Lacey to another location·View the Washington parking rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.