Key Facts
- Authority
- Tex. Local Gov't Code § 232.007
- Plan review deadline
- 60 days, County Engineer
- Final inspection
- within 2 business days of completion notice
- Certificate issued
- within 5 business days if compliant
- Utility hookup
- barred until certificate of compliance issued
- Enforcement
- District Attorney injunction suit
- Adopted
- Court Order No. 32, Jan. 27, 2004
Summary
Before a manufactured home rental community in unincorporated Brazoria County can open, the County Engineer must approve an infrastructure development plan, inspect construction, and issue a certificate of compliance. Utilities cannot connect water, sewer, gas or electric service to the community until the owner provides that certificate. The program runs under Commissioners Court Order No. 32.
6.1. Construction of a manufactured home rental community may not begin or proceed until the County Engineer has approved the infrastructure plan for the project. 6.2. The County Engineer shall perform such inspections on the ongoing construction as he or she deems appropriate. 6.3. On written confirmation by the owner of the manufactured home rental community that construction is complete, the County Engineer shall perform a final inspection within two (2) business days of receipt of such confirmation. 6.4. If the manufactured home rental community is found to comply with the infrastructure development plan, the County Engineer, as designated in this order by the Commissioners' Court to issue a certificate of compliance, shall issue such certificate within five (5) business days of the completion of the final inspection.
Full Breakdown
1 as land split into two or more spaces rented, leased or offered for lease for less than sixty months without a purchase option. Under § 4, the owner must submit an infrastructure development plan to the County Engineer covering the surveyed boundaries, proposed space locations, utility and drainage easements, right-of-way dedications, FEMA 100-year flood plain areas, a water supply meeting Health and Safety Code Chapter 341 Subchapter C, sewage service meeting Chapter 366 and 30 TAC Chapter 285, road access built to the Brazoria County Subdivision Regulations, and drainage designed to the county's Drainage Criteria Manual.
Section 5 gives the County Engineer sixty days from submittal to approve or reject the plan in writing; a plan not rejected inside that window is deemed approved. Section 6 controls construction itself: work may not begin until the plan is approved, the Engineer inspects ongoing construction as he or she deems appropriate, and once the owner confirms completion in writing the Engineer must perform a final inspection within two business days. A compliant community gets a certificate of compliance within five business days of that final inspection; a non-compliant one instead gets a written list of the non-complying elements on the same five-day clock.
Section 7 gives the certificate teeth: municipalities, municipally owned utilities, public utilities, nonprofit water or sewer corporations organized under Water Code Chapter 67, counties, and special districts are all barred from turning on water, sewer, gas or electric service to the community or any home in it until the owner hands over that certificate.
Violations & Fines
There is no ordinance fine schedule here. Section 8 sends enforcement straight to court: at the Commissioners Court's request, the District Attorney files suit in a court of competent jurisdiction to enjoin a threatened violation of these regulations. Practically, the certificate requirement in § 7 does the heavy lifting: without it, no utility, municipal or private, may lawfully connect water, sewer, gas or electric service to the community or its homes.
Frequently Asked Questions
Does a manufactured home rental community need county approval before construction starts?
How long does the County Engineer have to review the plan?
Can a utility connect service before the certificate is issued?
What happens if the county finds the community doesn't comply?
Sources & Official References
Other rules in Brazoria County
Texas rules heatmap·Compare Brazoria County to another location·View the Texas rental inspections overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.