Bowling Green, KY Sidewalk & Pedestrian Rules: Encroachment Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Governing section
Sec. 21-4.06
Permit lead time
5 days before non-emergency work
Emergency permit deadline
2 business days after discovery
Permit fee
$75 flat (Sec. 21-4.07)
Surety bond
$250 minimum, or $100,000 running bond
Covers
Cuts, excavation, lane/street/sidewalk closures
Penalty
Stop Work Order, Chapter 27 civil penalties

Summary

Any private cut, excavation or placement of facilities in a Bowling Green right-of-way needs a right-of-way work permit under Sec. 21-4.06, a $75 fee, and a surety bond, with applications due at least five days before non-emergency work begins and within two business days for emergencies.

a. Unless otherwise exempted by this Subchapter, any party performing any activity within the right-of-way that requires a permit pursuant to this Subchapter shall obtain the applicable permit prior to the performance of such activity and pay any applicable permit fee. ... ... e. A right-of-way permit shall be required for any cut or excavation or work in any City right-of-way. This includes any work that may require any lane closure and/or complete closure on a City-maintained street, alley, sidewalk or multi-use path. ... Permit fees in the amount of seventy-five dollars ($75) are required by this Subchapter and shall be paid at the time of application.

Full Breakdown

Sec. 21-4.06(a) requires any party performing an activity in the right-of-way that needs a permit under the Cuts, Excavations and Work Within Right-of-Way subchapter to obtain that permit and pay the applicable fee before starting, unless the Subchapter specifically exempts the work. Sec. 21-4.06(b) requires a non-emergency right-of-way work permit application at least five days before the planned activity, though the City Engineer can waive that lead time for good cause, and the Department must approve, deny or conditionally approve the application within five business days, stating in writing the basis for any denial or condition; work performed without proper notification is treated as work done without a permit and risks fines.

Emergency permits must be applied for within two business days of discovering the emergency. Sec. 21-4.06(e) confirms the core encroachment trigger for this target: a right-of-way permit is required for any cut or excavation or work in any City right-of-way, including work that requires closing a lane or fully closing a City-maintained street, alley, sidewalk or multi-use path. Applications are available from the Department and the City's website under Sec. 21-4.06(d), and Sec. 21-4.06(j) lets the City Engineer deny or revoke a permit that fails to meet the Subchapter's requirements or threatens public health, safety or welfare, while conditioning approval on specific requirements is also allowed.

Sec. 21-4.07 sets the flat cost: permit fees of $75 are required and due at the time of application. Sec. 21-4.08 backs every permit with a surety bond, minimum $250 for a single permit or $100,000 for an annual running bond covering multiple permits, released after a bond release inspection ninety days after the final repair.

Violations & Fines

Excavating or working in the right-of-way without the Sec. 21-4.06 permit, or without giving proper advance notice, is treated as work done without a permit under Sec. 21-4.06(b) and exposes the responsible party to fines, permit denial or revocation under Sec. 21-4.06(j), and a Stop Work Order under Sec. 21-4.19 for construction started before final approval or without any permit application, plus civil penalties under Chapter 27 of the Code.

Frequently Asked Questions

Do I need a permit to dig up the sidewalk or street in Bowling Green?
Yes. Sec. 21-4.06(e) requires a right-of-way permit for any cut, excavation or work in a City right-of-way, including work that closes a lane or fully closes a City-maintained street, alley, sidewalk or multi-use path.
How much does a right-of-way work permit cost in Bowling Green?
Sec. 21-4.07 sets a flat $75 permit fee due at the time of application, and Sec. 21-4.08 also requires a surety bond, with a $250 minimum for a single permit or $100,000 for an annual running bond covering multiple permits.
How far ahead do I need to apply for a right-of-way permit?
Sec. 21-4.06(b) requires non-emergency applications at least five days before the planned work, though the City Engineer can waive that for good cause, while an emergency permit must be applied for within two business days of discovering the emergency.

Sources & Official References

Other rules in Bowling Green

All Bowling Green rules

Compare Bowling Green to another location·View the Kentucky sidewalk & pedestrian rules overview

Get notified when Encroachment Permits in Bowling Green, KY changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.