Bristol Township, PA Sidewalk & Pedestrian Rules: Encroachment Permits (2026)
Key Facts
- Permit required
- Before opening or breaking any street, sidewalk, footpath or curb
- Where to apply
- Office of Licenses, Zoning and Inspections
- Minimum bond
- Not less than $1,000
- Permit term
- 30 days, renewable for a like period
- Emergency openings
- Permit within 72 hours after work starts
- Maximum penalty
- $1,000 plus costs, up to 30 days imprisonment in default
Summary
In Bristol Township, Bucks County, Pennsylvania, no one can open or break the surface of a street, sidewalk, footpath or curb without first obtaining a permit under § 175-17. Applications go through the Office of Licenses, Zoning and Inspections, carry a bond of not less than $1,000, and the permit runs 30 days unless it states a shorter period.
It shall be unlawful for any person or persons, firm, association or corporation to open or break the surface of the ground within the boundaries of any public highway, road, street, avenue, public lane, public alley, sidewalk or footpath for the purpose of installing pipes, sewers, drains or conduits of any description, for making connections therewith or repairs thereto or for the setting or planting of telephone, electric light or other poles or for repairs thereto or renewals thereof or to break the surface of any improved sidewalk or curb for the purpose of building any driveway apron across the same or for any other purpose without first obtaining from said Township Council a permit therefor before such work is begun and complying with the other requirements herein specified. It shall also be unlawful for any person or persons, firm, association or corporation to install or reinstall curbing or excavate without first obtaining a permit from the Bristol Township Office of Licenses, Zoning and Inspections.
Full Breakdown
Article III of Chapter 175 of the Bristol Township Code governs excavations and maintenance in public streets. Section 175-17 makes it unlawful for any person, firm, association or corporation to open or break the surface of the ground within any public highway, road, street, avenue, public lane, public alley, sidewalk or footpath to install pipes, sewers, drains or conduits, to make connections or repairs, or to set or plant telephone, electric light or other poles, without a permit from the Township Council before work begins. Breaking the surface of an improved sidewalk or curb to build a driveway apron needs the same permit. Installing or reinstalling curbing, or excavating, also requires a permit from the Bristol Township Office of Licenses, Zoning and Inspections.
The written application is filed with that office on a form the Township furnishes. It must state the purpose for which the street, sidewalk or footpath is to be opened, excavated or occupied and the location of the work, and the applicant agrees to assume all liability for damage to persons or property. For an emergency opening, a permit must be obtained within 72 hours after the work starts (§ 175-18).
The application is filed with a bond payable to the Township, in the amount the Township requires but not less than $1,000 (§ 175-19). For a homeowner's primary residence, the bond can be waived where the reasonable cost of the work does not exceed $500. The Township can also require a certificate of insurance with limits of $50,000/$100,000 for public liability and $25,000 for property damage. Occupying the permit area with building or construction materials carries its own fee for the first 24 hours and each day after (§ 175-20).
Permit and inspection fees are set by resolution or ordinance of Township Council. Unless it states a shorter period, a permit is good for 30 days and can be renewed for a like period on payment of a renewal fee (§ 175-21). It must be kept by a competent person on the work and shown on demand to any police officer or authorized employee. Work must start within the time in the permit, or within 24 hours after receipt where none is stated, and no permit area can be closed to traffic without the Township Engineer's written consent (§ 175-22).
Violations & Fines
A person who violates Article III faces, on conviction, a fine not to exceed $1,000 plus costs of prosecution, and in default of payment imprisonment for a term not to exceed 30 days (§ 175-32). If a permit holder fails to install or maintain temporary paving, the Township performs the work and charges the cost to the applicant. Defects in permanent paving that appear within one year because of defective backfilling must be repaid to the Township.
Frequently Asked Questions
Do I need a permit to cut a driveway apron across a sidewalk in Bristol Township?
What if a utility line breaks and the street has to be opened right away?
Can a homeowner skip the bond in Bristol Township?
How long does a Bristol Township opening permit last?
Sources & Official References
Other rules in Bristol Township
Compare Bristol Township to another location·View the Pennsylvania sidewalk & pedestrian rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.