Brockton, MA Sidewalk & Pedestrian Rules: Encroachment Permits (2026)

Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permitting authority
DPW Commissioner (awarding authority)
Permit term
30 days, renewable once
Advance notice required
72 hours
Deposit release window
6 months after final inspection
General liability minimum
$2,000,000 aggregate

Summary

Anyone excavating in a Brockton public way, including installing or realigning a driveway, must first get a street opening permit from the DPW commissioner as awarding authority. The permit costs an application fee plus a refundable restoration deposit and is void after 30 days unless renewed.

No work (except the commencement of emergency repair work in accordance with paragraph VII hereof) in or under a street of way shall commence until the applicant shall have applied for in accordance with paragraph IV, and obtained from the awarding authority or his representative, a street opening permit... No person or entity may perform any work (including street opening work or emergency repair work) in or under a street or way unless it is a permit holder and (i) is a municipal department or public utility or their respective officers or employees (ii) is the holder of a current and valid department of public works construction license, or (iii) has engaged such a holder and such holder performs all such street opening work or emergency repair work.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 28).

Full Breakdown

Sec. 20-39 covers excavation in a public way to install, repair, or remove utilities, or to install or realign a driveway, including removing or realigning curbing or fencing, and applies the by-law's requirements to that private encroachment work. Sec. 20-41 bars any work in or under a street until the applicant has applied and received a street opening permit from the awarding authority, the Commissioner of the Department of Public Works, or a representative; only a municipal department, public utility, licensed DPW construction contractor, or someone who has hired such a licensed holder may perform the work.

Sec. 20-42 requires a completed application with plans, insurance certificates, the application fee, and the refundable deposit, filed each time work is desired; the awarding authority weighs the DPW highway section's recommendation, the reason for the work, whether the street was recently paved, and whether other means could accomplish the purpose, and must communicate in writing if an application is not favorably considered. Sec. 20-43 sets the refundable deposit at an amount the awarding authority reasonably determines based on the scope of work, released after a final inspection following one year of completed permanent repairs, with a request for release due within six months of that inspection or the deposit is forfeited.

Sec. 20-48 fixes the permit term at 30 days, renewable once for another 30 days on written request, and allows revocation for default; it requires 72 hours' notice before work, a Dig-Safe number, and written consent from the DPW commissioner or designee before removing any tree or shrub in a planting strip.

Violations & Fines

Performing street opening work, including installing or realigning a driveway in the public way, without a valid permit or without being a licensed DPW construction contractor violates Sec. 20-41. A permit holder in default, including failure to maintain the required insurance and bond, can have the permit revoked under Sec. 20-48(1), and the awarding authority can draw on the applicant's refundable deposit account to fund proper repairs under Sec. 20-43.

Frequently Asked Questions

Do I need a city permit to install a new driveway across the sidewalk in Brockton?
Yes. Sec. 20-39 specifically covers installing or realigning a driveway, including removal or realignment of curbing or fencing, as street opening work requiring a permit from the DPW commissioner under the procedures in Sec. 20-41 and 20-42.
How long is a Brockton street opening permit valid?
Sec. 20-48(1) sets the term at 30 days from issuance, renewable for one additional 30-day period on written request to the awarding authority, and the permit must be present at the work site at all times.
Can I remove a tree in the planting strip while doing street opening work?
No, not without consent. Sec. 20-48(7) prohibits removing, even temporarily, any tree or shrub in a planting strip area without first obtaining the consent of the commissioner of the department of public works or a designee.

Sources & Official References

Other rules in Brockton

All Brockton rules

Compare Brockton to another location·View the Massachusetts sidewalk & pedestrian rules overview

Get notified when Encroachment Permits in Brockton, MA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.