Chapel Hill, NC Sidewalk & Pedestrian Rules: Encroachment Permits (2026)
Key Facts
- Permit required
- Before any street/sidewalk cut or public improvement
- Issuing office
- Town manager, Chapel Hill
- Performance bond
- 125% of estimated construction cost
- Warranty bond
- 25% of cost or $50,000, whichever less
- Utility notice
- 24 hours before street-damaging work
- Penalty
- Misdemeanor for willful violation (§ 17-49)
Summary
Anyone cutting pavement, curb or sidewalk in a Chapel Hill public street, or building sidewalks, driveways or utility lines the Town will maintain, must get a construction permit from the town manager under Code of Ordinances Section 17-42. The permit requires approved plans, paid fees and posted bonds, and willful violations are a misdemeanor under Section 17-49.
(1)Prior to the start of construction of any public street, paving, curb and gutter, sidewalks, storm drainage structure, water or sewer facility, or other public improvements (within the planning and zoning jurisdiction of the Town of Chapel Hill) that will ultimately be maintained by the Town of Chapel Hill, and also prior to the cutting of any pavement, curb or sidewalk in an existing public street, the person intending to do so shall obtain a construction permit from the town manager. A construction permit shall be issued only after plans for the construction, construction cost estimates, and other information required by the town manager, have been submitted to him; the town manager has approved said plans, has collected the appropriate fees set forth in the most recent schedule of fees adopted by the council, and has received the appropriate bonds. ... Willful violation of any provision of this article shall be a misdemeanor.
Full Breakdown
Article IV of Chapter 17, Construction Permits, governs any private encroachment into the Town's streets and sidewalks. Section 17-42 requires a construction permit from the town manager before starting construction of any public street, paving, curb and gutter, sidewalk, storm drainage structure, water or sewer facility, or other public improvement that the Town will ultimately maintain, and before cutting any pavement, curb or sidewalk in an existing public street. To get the permit, the applicant must submit construction plans and cost estimates, have the town manager approve those plans, pay the fees set in the Town's current fee schedule resolution, and post the required bonds.
Section 17-45 sets the bond amounts: a performance bond of one hundred twenty-five percent of the estimated construction cost, and, once work is complete, a one-year warranty bond of twenty-five percent of the project cost or fifty thousand dollars, whichever is less; the town manager may waive both bonds for a project under ten thousand dollars if the contractor has no outstanding obligations to the Town. Section 17-43 lets the town manager suspend or revoke a permit for noncompliance, stopping all work until the permit is reinstated and a reinstatement penalty is paid.
Franchised utility companies are exempt from the permit itself under Section 17-42(3), but must still notify the town manager's office twenty-four hours before construction that will damage a public street or significantly obstruct traffic, and must pay street cut assessments. Anyone cutting into a state-maintained street must also obtain the North Carolina Department of Transportation's own encroachment agreement in addition to the Town's permit. Willful violation of the article, including working without a permit, is a misdemeanor under Section 17-49.
Violations & Fines
Cutting pavement, curb or sidewalk, or building street improvements the Town will maintain, without first getting a Section 17-42 construction permit is a willful violation of Article IV and a misdemeanor under Section 17-49. The town manager can also suspend or revoke an existing permit under Section 17-43 for noncompliance, halting all work until it is reinstated and a penalty paid.
Frequently Asked Questions
Do I need a permit to cut a curb in Chapel Hill?
How big a bond does a Chapel Hill street permit need?
Are utility companies exempt from Chapel Hill's street cut permit?
Sources & Official References
Other rules in Chapel Hill
Compare Chapel Hill to another location·View the North Carolina sidewalk & pedestrian rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.