Key Facts
- Permit required for
- driveways, culverts, utility lines, ROW crossings
- Unpermitted work penalty
- 4x normal permit fee (Sec. 3-6-28(b))
- Pavement/intersection work bond
- 110% of project cost
- Permit expires if inactive
- 6 months from issuance
- Liability insurance minimum
- $300,000 combined limit
- Apply through
- community development building division
Summary
Charlotte County requires a right-of-way permit before anyone builds, installs or alters a driveway, culvert, utility line, drainage swale or other facility in a county road right-of-way or easement. Section 3-6-24 covers driveway work, temporary ROW crossings for pools or septic systems, utility installation, sod and landscaping, and pavement construction or repair.
(a)Except as provided in section 3-6-25, it shall be unlawful for any person, municipal corporation, special district, or any other legal entity to construct, install, remove, revise, alter, or modify any structure, facility, or topographic feature on any land, right-of-way or easement owned by the county, or any right-of-way dedicated to the public, without first having obtained a permit from the county. Activities requiring a permit include, but are not limited to:(1)Installation, re-installation or resurfacing of driveways;(2)Installation of culvert pipe;(3)All activities requiring temporary access across the ROW, including, but not limited to, house moving, swimming pool construction, septic system installation;(4)All storm water drainage facilities and associated work, including, but not limited to, swale grading;(5)All overhead or underground utility installation, including, but not limited to, sanitary sewer, water lines, electric conductors, conduit, cable television, and communication devices;(6)Sod and landscaping installation;(7)Temporary material or equipment storage; and(8)Pavement construction or repair.
Full Breakdown
Section 3-6-24(a) makes it unlawful to construct, install, remove, revise, alter or modify any structure, facility or topographic feature on county-owned or publicly dedicated right-of-way without first getting a permit, except for the narrow exemptions in section 3-6-25: routine trimming of existing trees and shrubs done under chapter 3-9, article IV, and mailboxes that meet federal, state and local rules. Applications go to the building division of the community development department under section 3-6-29 and must include the applicant's and agent's contact and license information, scaled dated drawings of the proposed work, a maintenance-of-traffic plan, underground-installation detail where relevant, a subcontractor list, and professional-engineer-sealed drainage or pavement plans for private-road connections or intersection work.
Section 3-6-30 ties the permit's duration to the period the county specifies, allows one no-charge extension at the county's discretion, and lets a permit expire, with no refund, if it is not activated within six months. Pavement or intersection-improvement permits additionally require a development agreement and a surety or cash bond equal to one hundred ten percent of the work's cost under section 3-6-31. 4 requires the permittee to carry comprehensive general liability coverage with a three-hundred-thousand-dollar combined limit and to name the county as an additional insured.
Violations & Fines
Working in the right-of-way without an approved permit triggers quadruple the normal permit fee under section 3-6-28(b), on top of any separate code enforcement violation penalty, and the county can deny the application outright and require the right-of-way restored to its earlier condition at the violator's expense. The county engineer can also rescind a permit issued in error, including one obtained through a misrepresentation on the application, under section 3-6-32.
Frequently Asked Questions
What work needs a right-of-way permit in Charlotte County?
Is anything exempt from the right-of-way permit?
How long does a right-of-way permit last, and can it be extended?
What happens if I do the work without getting a permit first?
Sources & Official References
Other rules in Charlotte County
Florida rules heatmap·Compare Charlotte County to another location·View the Florida sidewalk & pedestrian rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.