Richland County, SC Sidewalk & Pedestrian Rules: Encroachment Permits (2026)
Key Facts
- Permit issued by
- county engineer's office
- Max street width opened at once
- one-half (1/2)
- Failure-to-maintain period
- 1 year
- Covers
- curb cuts, utility taps, drainage lines, signs
- Cost recovery on default
- charged against permit bond
Summary
Digging, tapping utilities, or cutting a curb along a county road in unincorporated Richland County requires an encroachment permit from the county engineer's office before work starts, and the permit holder must indemnify the county for any resulting damage.
(a) Generally. (1) An encroachment permit, approved by the county engineer's office, shall be required for all construction, undertaken by parties other than the county public works department or its authorized contractor, within or affecting the right-of-way of any county maintained highway, street or road... (2) The permittee shall indemnify the county for any liability incurred or damages sustained as a result of the encroachment. (b) Excavations in streets. (1) An encroachment permit shall be required for each excavation in a county road before the work is commenced... There shall be no more than one-half (1/2) the width of any street or alley opened or obstructed at any one time; tunneling may be allowed, provided that no authorized underground construction shall be damaged or interfered with.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2026 S-24: This supplement is current through Ordinance No. 033-25HR).
Full Breakdown
Sec. 21-24 requires an encroachment permit, approved by the county engineer's office, for any construction within or affecting the right-of-way of a county-maintained highway, street or road when the work is done by someone other than the county's own public works department or its authorized contractor. The section lists specific triggers: driveway connections involving a curb cut or pipe installation, curb cuts generally, utility taps, utility installations, excavations within the right-of-way, storm drainage installation, storm drainage discharge, and subdivision entrance signs or gateways, though the list is explicitly non-exclusive.
The permittee must indemnify the county for any liability or damages the encroachment causes, notify the county engineer's office when construction begins, keep a copy of the permit on site during the work, and ensure the county engineer's office approves both the construction and the roadway restoration. Subsection (b) adds street-excavation specifics: work must start within the time the permit specifies or the permit becomes void, no more than half the width of a street or alley may be opened or obstructed at one time (tunneling is allowed instead), and any paving removed for the excavation must be restored to as good a condition as before, with the permit holder required to notify public works in writing when the trench is refilled, tamped, and ready for repaving.
A permit holder who fails to properly refill an excavation, or fails to maintain the repair for a full year, faces the county doing the work itself and charging the cost against the bond posted for the permit.
Violations & Fines
A permittee who fails to refill an excavation properly or maintain it for one year has the work completed by the county at the permittee's expense, charged against the bond posted when the permit was issued. The permittee also bears indemnification liability for any damage the encroachment causes to the county's right-of-way.
Frequently Asked Questions
Do I need a permit to cut a curb for my driveway in unincorporated Richland County?
How much of the street can a contractor block during a utility excavation?
What happens if I don't properly restore the road after excavating?
Sources & Official References
Other rules in Richland County
Compare Richland County to another location·View the South Carolina sidewalk & pedestrian rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.