Pinal County, AZ Sidewalk & Pedestrian Rules: Encroachment Permits (2026)
Key Facts
- Permit issuer
- Pinal County Engineer
- Advance notice before work
- 48 hours
- Minimum backfill base
- 6 inches of aggregate
- Cable clearance from section line
- 20 feet minimum
- Pole clearance from right-of-way edge
- Max 5 feet
- New-street cut moratorium
- 1 year, emergencies only
- Workmanship warranty
- 1 year from acceptance
Summary
In unincorporated Pinal County, no one may build a driveway, sidewalk, curb, gutter or pavement, or install pipelines, cables or signs in a county road right-of-way without a permit from the county engineer. Pavement cuts also trigger restoration fees and repair standards under the county's rights-of-way chapter.
No person, corporation, association or political subdivision shall, without first obtaining a permit from the office of the county engineer, enter upon the right-of-way of any public road, street or alley not a state highway, and outside the corporate limits of any city or town for the purpose of: (1) Constructing, installing, reconstructing or removing any pavement, driveway, sidewalk, curb or gutter; ... (5) Erecting any structure or sign on or overhanging the right-of-way.
Full Breakdown
Pinal County Code Chapter II of Title 18 governs all private use of public road, street and alley rights-of-way outside city and town limits. Section 18-21 requires a permit from the office of the county engineer before anyone enters the right-of-way to construct, install, reconstruct or remove pavement, driveway, sidewalk, curb or gutter; to install or remove water, gas, sewer or irrigation lines; to install or remove power or communications systems; or to erect a structure or sign on or overhanging the right-of-way. Section 18-22 requires a written application on the county's form, accompanied by two sets of drawings or blueprints showing the proposed work and specifications, plus a subgrade soil laboratory report if the county engineer requires one.
Section 18-23 sets minimum construction standards: pavement cuts must receive at least six inches of approved aggregate base, with two inches of asphaltic pavement added over cuts in bituminous pavement; underground power and communication cables must sit at least 20 feet from the section line; power and communication poles may not sit more than five feet from the edge of the right-of-way; and backfilling must be mechanically tamped and completed within three days of pipe or cable installation at any point crossing a county road.
The permittee must notify the county engineer 48 hours before work begins and assumes full liability for injury or damage arising from the permitted work. Section 18-24 adds pavement-restoration requirements: no street cut is allowed within one year of new construction or reconstruction of a street except case-by-case emergency cuts, and cuts made in year one to two require either a fee under the county fee schedule or, at the applicant's election, a two-inch asphalt mill-and-overlay treatment extending at least 18 feet in both directions from the cut.
Cuts under two square feet are fee-exempt (capped at three per project) but still require a slurry seal treatment extending at least 25 feet in both directions. All work is guaranteed against defective workmanship for one year from acceptance.
Violations & Fines
Undertaking right-of-way work before a permit is issued requires the work to be stopped until a permit is secured (Sec. 18-23(8)a). The county engineer can revoke a permit and order the permittee to remove all property from the right-of-way if the county later needs that space (Sec. 18-23(8)g). A permittee whose work fails final inspection must remove or replace it within the time set by the county's written notice, and any later-discovered defective material must be replaced with material the county specifies (Sec. 18-23(8)e). Emergency cuts not reported to public works the same day, or by the next business day after hours, risk violation and associated penalties (Sec. 18-24(1)a).
Frequently Asked Questions
Do I need a permit to install a driveway or sidewalk in Pinal County?
What has to be included in the application?
Can I cut a brand-new street?
What happens if I do the work without a permit first?
Sources & Official References
Other rules in Pinal County
Compare Pinal County to another location·View the Arizona sidewalk & pedestrian rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.