Key Facts
- Permit required for
- Driveways, sidewalks, drainage, mailboxes, signs in ROW
- Issuing authority
- County Administrator
- Initial term
- Six months from approval
- Maximum extension
- Twelve months total, then new application
- Application format
- Submitted in triplicate, one original
- Revocation grounds
- Non-compliance, misrepresentation, or safety hazard
Summary
St. Johns County requires a Right-of-Way Permit from the County Administrator before anyone builds a driveway connection, sidewalk, drainage alteration, mailbox, sign, or similar improvement within county right-of-way. The permit runs six months from approval and can be extended to a total of twelve months before a brand-new application is required.
An "Application for Right-of-Way Permit" shall be submitted to, and approved by, the County Administrator prior to commencement of any planned Construction activities within County right-of-way. Construction activities include, but are not limited to: utility installations, driveway connections, sidewalks, drainage alterations, placement of mailboxes, Signs, and similar Construction activities that normally occur within the right-of-way, unless exempted by provisions of Section 6.04.04.B. Right-of-Way Permits shall not be required for Construction activities that are approved through a "Development Permit" subject to the provisions of Part 9.01.00 herein.
Full Breakdown
Section 9.01.05 of the Land Development Code requires an Application for Right-of-Way Permit to be submitted to, and approved by, the County Administrator before any construction begins in county right-of-way in unincorporated St. Johns County. The section names the activities that trigger it: utility installations, driveway connections, sidewalks, drainage alterations, and placement of mailboxes or signs, along with similar work that normally occurs within the right-of-way, though the permit is not required when Section 6.04.04.B exempts the activity or when the work is already covered by an approved Development Permit under Part 9.01.00.
The companion design standard, Section 6.04.04, spells out the same prohibition from the construction side and lists what counts as a regulated structure or utility, including fences, landscaping, drainage connections, cross drains, side drains, ditches, and swales, and gives the County Administrator authority to revoke a permit if the work departs from the approved conditions, if the application misrepresented a material fact, or if the activity threatens public health, safety, or welfare. Applications must be submitted in triplicate, with one original, and once approved the applicant keeps a copy on the job site for county inspectors, while the county's copy goes to its inspection staff.
Section 9.01.05.C caps an approved permit at six months from the date of approval; the County Administrator can extend it in writing up to a total of twelve months, and anything beyond that requires a brand-new application, drawings, and payment of the applicable fees all over again.
Violations & Fines
Starting work in county right-of-way without an approved Right-of-Way Permit is prohibited outright under Section 9.01.05.A and Section 6.04.04.B, and the County Administrator can revoke a permit already issued if the work doesn't match the approved conditions, if the application misrepresented a material fact, or if the activity endangers public health, safety, or welfare, halting the encroachment until a compliant application is submitted.
Frequently Asked Questions
Do I need a permit to put a mailbox or sign in the right-of-way in St. Johns County?
How long does a St. Johns County right-of-way permit last?
Can the county take back a right-of-way permit once it's issued?
Sources & Official References
Other rules in St. Johns County
Florida rules heatmap·Compare St. Johns County to another location·View the Florida sidewalk & pedestrian rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.