Pasadena, CA Solar Energy: Expedited Solar Permitting (2026)
Key Facts
- Adopted
- Ordinance No. 7267 (Oct. 5, 2015)
- Governing state law
- Gov't Code § 65850.5
- Required inspections
- single inspection, standard case
- HOA approval
- not required for permit
- Submittals
- electronic applications & signatures accepted
- Checklist source
- California Solar Permitting Guidebook
Summary
Pasadena's Expedited Permitting Procedures for Small Residential Rooftop Solar Systems ordinance requires the building official to run a ministerial, checklist-based review for qualifying small rooftop solar installations under Government Code Section 65850.5. Applicants can submit electronically, an HOA cannot block permit approval, and the city allows only one inspection unless the system fails it.
Solar energy systems which qualify for expedited permit processing pursuant to Government Code Section 65850.5 shall be subject to the administrative and ministerial permitting procedures set forth in this chapter. Consistent with Government Code Section 65850.5, the building official shall implement an expedited administrative permit review process for small rooftop solar energy systems, and adopt a checklist of all requirements with which small rooftop solar energy systems shall comply in order to be eligible for expedited review. The expedited administrative permit review process and checklist shall substantially conform to the recommended process and checklist prescribed by the California Solar Permitting Guidebook as adopted by the Governor's Office of Planning and Research. The city's adopted checklist shall be published on the city's website.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 79 Update 2).
Full Breakdown
Chapter 14.90, adopted by Ordinance No. 7267 in 2015, implements the state's solar permitting mandate at the local level. Section 14.90.030 directs the building official to publish a checklist on the city's website that substantially conforms to the California Solar Permitting Guidebook issued by the Governor's Office of Planning and Research, and any application meeting that checklist must be processed administratively rather than through discretionary review. Section 14.90.040 requires the building official to accept electronic submittal of permit applications and supporting documents, and to accept electronic signatures in place of a wet signature. Section 14.90.050 bars the building official from conditioning approval of a solar permit on approval by a homeowners association, as defined by Civil Code Section 4080.
Under Section 14.90.060, an application that satisfies the checklist must be deemed complete and processed; if the building official finds it incomplete, a written correction notice detailing every deficiency must be issued. Approval of the permit does not authorize connecting the system to the utility grid, which the applicant must arrange separately with Pasadena Water and Power. Section 14.90.070 limits the city to a single inspection for a qualifying small residential rooftop system, though a failed inspection allows follow-up inspections. The definitions used throughout the chapter track Government Code Section 65850.5, per Section 14.90.020.
Violations & Fines
There is no fine schedule inside Chapter 14.90 itself; instead of penalties, the ordinance channels noncompliance into a correction process. If a submitted application does not meet the city's checklist, Section 14.90.060 requires the building official to issue a written correction notice identifying every deficiency rather than deny the application outright, and the applicant must correct and resubmit before the expedited track applies. Systems that fail the single required inspection under Section 14.90.070 face an additional inspection rather than a monetary penalty, and connecting an approved system to the grid without the utility's separate sign-off remains the applicant's responsibility, not the city's.
Frequently Asked Questions
Does Pasadena require HOA approval before installing solar panels?
How many inspections does a small rooftop solar system need?
Can I submit my Pasadena solar permit application online?
What happens if my solar application is missing information?
Sources & Official References
Other rules in Pasadena
California rules heatmap·Compare Pasadena to another location·View the California solar energy overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Expedited Solar Permitting in Nearby Cities
How other cities in Los Angeles County handle expedited solar permitting.