Key Facts

Rooftop/small ground solar
Administrative approval, accessory use
Large ground systems/solar farms
Special use permit from board
Ground system height cap
15 feet at maximum tilt
Ground system noise cap
45 dBA at property line
Building permit
Required for building- and ground-mounted systems
Solar farm minimum size
10 to 500 acres

Summary

Coweta County treats rooftop and small-scale ground solar as an accessory use in every zoning district, but still requires the community development director's sign-off and a building permit. Sec. 6D.7 of the Solar Energy Ordinance sets that administrative review track, while larger ground-mounted systems and solar farms need a special use permit from the board of commissioners.

These county ordinances apply to unincorporated areas of Coweta County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

a.Administrative review and approval.1.Building mounted solar energy systems shall be considered as an accessory use in all zoning districts; provided that the requirements of this solar energy ordinance are met and subject to the director of community development's approval with or without conditions, as applicable.2.Small-scale ground mounted solar energy systems shall be considered as an accessory use in all zoning districts; provided that all requirements of this solar energy ordinance are met and subject to the director of community development's approval with or without conditions, as applicable.... Permitting: A building permit is required for installation of all building mounted solar energy systems. ... Permitting. A building permit is required for any ground-mounted solar energy system and for the installation of any thermal solar energy system.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 40).

Full Breakdown

Coweta County's Solar Energy Ordinance, added to Article 6D of the Zoning and Development Ordinance in 2025, sorts solar projects into two approval tracks. Sec. 6D.7(a) puts building-mounted systems and small-scale ground-mounted systems (footprint under one acre) on administrative review: both "shall be considered as an accessory use in all zoning districts," subject to the director of community development's approval, with or without conditions. Sec. 6D.7(b) pushes intermediate- and large-scale ground-mounted systems, and solar farms over ten acres, into a special use permit reviewed and approved by the board of commissioners, and limits those larger projects to the LM, M, and RC zoning districts.

Permitting requirements differ by installation type under Sec. 6D.10. Every building-mounted system needs a building permit, and panels on a sloped roof cannot rise above the roof's highest point; on a flat roof, panels cannot extend past the roofline. Ground-mounted systems also need a building permit, cannot sit in a front yard or between the house and the street, must stay at least ten feet from any structure, cannot exceed 15 feet in height at maximum tilt, and are capped at 25 percent of the principal building's footprint on residential lots. Inverter noise from a ground system cannot exceed 45 dBA at the property line.

Applications for anything beyond a small rooftop or small ground system trigger the fuller submittal package under Sec. 6D.8: application and permit fees, a surveyor's site plan, an elevation sketch, and, for solar farms, a decommissioning plan with financial assurance so the county isn't left to cover removal costs if a project is abandoned.

Violations & Fines

Installing a solar energy system without the required building permit, special use permit, or administrative approval under Sec. 6D.7 is a zoning violation enforced by the Coweta County Department of Community Development. The Solar Energy Ordinance sets no separate fine, so the general penalty in Code § 1-15 applies: up to $1,000, up to 60 days imprisonment, or both, with each day of noncompliance treated as a separate offense.

Frequently Asked Questions

Do I need a permit to put solar panels on my roof in Coweta County?
Yes. Sec. 6D.10(b)(4) requires a building permit for every building-mounted solar energy system, even though Sec. 6D.7(a) treats rooftop solar as an accessory use allowed administratively in every zoning district without a special use permit or board hearing.
How big can a ground-mounted solar system be before I need board approval instead of a staff sign-off?
A small-scale ground-mounted system, footprint under one acre, only needs administrative approval from the director of community development. Once the footprint reaches one acre, Sec. 6D.7(b) reclassifies it as intermediate- or large-scale and requires a special use permit from the board of commissioners in the LM, M, or RC districts.
How tall can my ground-mounted solar panels be in Coweta County?
Sec. 6D.10(c)(3) caps a ground-mounted solar energy system at 15 feet in height, measured at the maximum tilt angle used for solar collection, and the panels must sit at least ten feet from any principal building on the same lot.
What paperwork does a solar farm application need beyond a building permit?
Sec. 6D.8 requires a full submittal package for solar farms: application and permit fees, a surveyor's site plan, a noise evaluation report capped at 45 dBA at the property line, and a decommissioning plan backed by financial assurance covering removal costs.

Sources & Official References

Other rules in Coweta County

All Coweta County rules

Compare Coweta County to another location·View the Georgia solar energy overview

Get notified when Panel Permits in Coweta County, GA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.