Key Facts

Accessory solar status
By-right in all zoning districts
Principal solar status
Conditional use only, all districts
Ground setback (principal)
75 feet from property line/right-of-way
Steep slope limit
No panels on slopes over 15%
Inspection
Biennial engineer's report for approved principal systems

Summary

Accessory rooftop or ground-mounted solar systems are a by-right use in every Franklin Township zoning district under Section 8-102, but a permit application still must show compliance with Township zoning, the PA Uniform Construction Code and manufacturer standards before construction starts. A principal, off-site-power solar facility instead needs Board of Supervisors conditional-use approval.

Except as otherwise provided in the Township Zoning Ordinance, systems shall be considered as an accessory use by right in all zoning districts. ... Prior to construction, a permit application shall be submitted for review and approval. The applicant shall show that all applicable manufacturer, Township (including zoning permits, PA Uniform Construction Code permits, etc., as adopted by the Township), Commonwealth of Pennsylvania, and any other applicable standards for the construction, operation and maintenance of the proposed system have been met. ... Permitted in all zoning districts only by conditional use in accordance with this section and § 27-2313. It shall be the applicant's burden to demonstrate satisfaction to the Board of Supervisors that all requirements of § 27-2313 have been met.

Full Breakdown

Chapter 8, Part 1 of the Franklin Township Code, added by Ordinance 2025-01 on February 19, 2025, splits solar regulation into two tracks. A; a property owner who cannot meet a specific design condition, or who proposes novel technology, can ask the Board of Supervisors for a waiver, granted by resolution at the Board's sole discretion. D requires a permit application demonstrating that the system meets applicable manufacturer standards, Township requirements including zoning permits and PA Uniform Construction Code permits, Commonwealth standards, and, where the system may feed power back to the grid, written utility approval of the interconnection.

Roof-mounted arrays can't extend past the roof edge or above a peaked roof's ridgeline; ground-mounted arrays must meet the underlying district's setbacks and height limits, stay off slopes over 15%, and avoid woodland disturbance without replacing the trees removed. A permits it in every district only by conditional use under Section 27-2313, with the applicant bearing the burden of proving compliance to the Board of Supervisors, plus land development and stormwater management plan approval, a 75-foot minimum setback from every property line and road right-of-way, and a biennial engineer's inspection report once approved.

Violations & Fines

Franklin Township enforces solar standards through its ordinary zoning and UCC permitting channels: building or operating a system without the required zoning permit, UCC permit, or Board of Supervisors conditional-use approval exposes the property owner to the Township's standard zoning enforcement and Uniform Construction Code penalty provisions. For a principal-use facility, Section 8-102.2.A also makes every conditional-use condition binding on later owners, recorded verbatim against the property, so a purchaser inherits the compliance obligations along with the land.

Frequently Asked Questions

Do I need a permit for rooftop solar panels in Franklin Township?
Yes. While Section 8-102 treats accessory solar as a by-right use in every zoning district, you still must submit a permit application showing the system meets manufacturer, Township zoning, PA Uniform Construction Code and Commonwealth standards before construction begins.
Can I build a large solar farm to sell power off-site?
Only with Board of Supervisors conditional-use approval under Section 8-102.2.A and Section 27-2313. You'll also need land development and stormwater management plan approval, a 75-foot setback from every property line and road, and a biennial engineer's inspection report once the system is running.
What if my solar project can't meet every design standard?
Section 8-102.1 lets an accessory-system applicant seek a waiver from the Board of Supervisors for a specific condition, novel technology, or de minimis relief. The Board can consult the Township Engineer or Code Enforcement Officer, but granting a waiver, by resolution, is entirely within the Board's discretion.

Sources & Official References

Other rules in Franklin Township

All Franklin Township rules

Compare Franklin Township to another location·View the Pennsylvania solar energy overview

Get notified when Panel Permits in Franklin Township, PA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.