Fruitport Charter Township, MI Solar Energy: Panel Permits (2026)
Key Facts
- Ordinance
- Ord. No. 807, effective April 3, 2019
- Exempt collectors
- Under five square feet and under five feet high
- Application items
- Renderings, elevation drawings, site plans with lot-line distances
- Ground-mounted front yard
- At least 150 feet from the front lot line
- Residential ground array
- One percent of lot area, up to 1,500 square feet
- Abandonment
- 12 months without energy production
Summary
In Fruitport Charter Township, Ordinance No. 807 requires every small-scale solar installation to submit equipment and unit renderings, elevation drawings and site plans showing distances from lot lines and adjacent structures, and to comply with building codes, electrical codes and other township and state requirements. Collectors under five square feet and less than five feet above the ground are exempt.
Sec. 42-690. Applicability. ... This article applies to any system of small-scale solar energy collector systems. This article does not apply to solar energy collectors mounted on fences, poles, or on the ground with collector surface areas less than five square feet and less than five feet above the ground, nor does this article apply to utility-scale solar energy collector systems. ... (1) Applications. In addition to all other required application contents as required by this chapter, equipment and unit renderings, elevation drawings, and site plans depicting the location and distances from lot lines and adjacent structures shall be submitted for review. No small-scale solar energy collector system shall be installed or operated except in compliance with this Chapter. ... a. A solar energy collector shall be permanently and safely attached to the ground or structure. Solar energy collectors, and their installation and use, shall comply with building codes, electrical codes, and other applicable township and state requirements.
Full Breakdown
Ordinance No. 807 added Article X (Secs. 42-690 to 42-693) to Chapter 42 for small-scale solar. The Township Board adopted it on March 11, 2019 and it took effect on April 3, 2019. Article X applies to any small-scale solar energy collector system, with one carve-out: collectors mounted on fences, poles, or on the ground with collector surface areas less than five square feet and less than five feet above the ground are outside the article, as are utility-scale systems.
The application step is § 42-691(1). On top of every other application item the chapter requires, the owner submits equipment and unit renderings, elevation drawings, and site plans depicting the location and distances from lot lines and adjacent structures. No small-scale system can be installed or operated except in compliance with the chapter. Separately, § 42-31 requires a certificate of zoning compliance and a building permit from the zoning administrator before a structure is erected, moved, enlarged or altered, and § 42-691(3)(a) requires installations to comply with building codes, electrical codes and other applicable township and state requirements. Installers follow the manufacturer's directions, a copy goes to the township on request before installation, and the applicant certifies that construction and installation meet or exceed the manufacturer's standards.
Building-mounted systems are accessory uses in all zoning districts. Their height cannot exceed the district maximum by more than three feet, and they cannot obstruct solar access to adjacent properties. Ground-mounted systems go in the rear or side yard subject to accessory-structure setbacks, or in the front yard only if at least 150 feet from the front lot line. Ground-mounted limits: one unit per principal building; for residential uses one percent of lot area up to 1,500 square feet of panels; for agricultural, commercial and industrial uses 10,000 square feet; maximum height six feet for residential and 16 feet for the others; minimum lot area 82,500 square feet; and screening where the unit impacts views from adjacent residential properties.
On-site power lines between panels and inverters go underground. A system that ceases to produce energy for 12 months is considered abandoned unless the owner gives the township evidence of intent to restart every six months, and removal and restoration are due within one year of abandonment. Utility-scale systems follow a separate special use track under Article XI.
Violations & Fines
Section 42-691(1) bars installing or operating a small-scale system except in compliance with the chapter. Zoning violations go to the building inspector under § 42-32(1): notice to cease, then if the owner fails to act diligently 14 days after notification, a second notice, notice to the township board and prosecution in court. Under § 2-156 a violation not designated a municipal civil infraction is a misdemeanor, fine up to $500.00 plus costs, or up to 90 days in jail.
Frequently Asked Questions
What must I submit to install solar panels in Fruitport Charter Township?
Do small solar collectors need approval?
How big can a ground-mounted array be on a residential lot?
What happens when a system stops producing power?
Sources & Official References
Other rules in Fruitport Charter Township
Compare Fruitport Charter Township to another location·View the Michigan solar energy overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.