Key Facts

Ordinance
Ord. No. 807, effective April 3, 2019
Exempt collectors
Under five square feet and under five feet high
Application items
Renderings, elevation drawings, site plans with lot-line distances
Ground-mounted front yard
At least 150 feet from the front lot line
Residential ground array
One percent of lot area, up to 1,500 square feet
Abandonment
12 months without energy production

Summary

In Fruitport Charter Township, Ordinance No. 807 requires every small-scale solar installation to submit equipment and unit renderings, elevation drawings and site plans showing distances from lot lines and adjacent structures, and to comply with building codes, electrical codes and other township and state requirements. Collectors under five square feet and less than five feet above the ground are exempt.

Sec. 42-690. Applicability. ... This article applies to any system of small-scale solar energy collector systems. This article does not apply to solar energy collectors mounted on fences, poles, or on the ground with collector surface areas less than five square feet and less than five feet above the ground, nor does this article apply to utility-scale solar energy collector systems. ... (1) Applications. In addition to all other required application contents as required by this chapter, equipment and unit renderings, elevation drawings, and site plans depicting the location and distances from lot lines and adjacent structures shall be submitted for review. No small-scale solar energy collector system shall be installed or operated except in compliance with this Chapter. ... a. A solar energy collector shall be permanently and safely attached to the ground or structure. Solar energy collectors, and their installation and use, shall comply with building codes, electrical codes, and other applicable township and state requirements.

Full Breakdown

Ordinance No. 807 added Article X (Secs. 42-690 to 42-693) to Chapter 42 for small-scale solar. The Township Board adopted it on March 11, 2019 and it took effect on April 3, 2019. Article X applies to any small-scale solar energy collector system, with one carve-out: collectors mounted on fences, poles, or on the ground with collector surface areas less than five square feet and less than five feet above the ground are outside the article, as are utility-scale systems.

The application step is § 42-691(1). On top of every other application item the chapter requires, the owner submits equipment and unit renderings, elevation drawings, and site plans depicting the location and distances from lot lines and adjacent structures. No small-scale system can be installed or operated except in compliance with the chapter. Separately, § 42-31 requires a certificate of zoning compliance and a building permit from the zoning administrator before a structure is erected, moved, enlarged or altered, and § 42-691(3)(a) requires installations to comply with building codes, electrical codes and other applicable township and state requirements. Installers follow the manufacturer's directions, a copy goes to the township on request before installation, and the applicant certifies that construction and installation meet or exceed the manufacturer's standards.

Building-mounted systems are accessory uses in all zoning districts. Their height cannot exceed the district maximum by more than three feet, and they cannot obstruct solar access to adjacent properties. Ground-mounted systems go in the rear or side yard subject to accessory-structure setbacks, or in the front yard only if at least 150 feet from the front lot line. Ground-mounted limits: one unit per principal building; for residential uses one percent of lot area up to 1,500 square feet of panels; for agricultural, commercial and industrial uses 10,000 square feet; maximum height six feet for residential and 16 feet for the others; minimum lot area 82,500 square feet; and screening where the unit impacts views from adjacent residential properties.

On-site power lines between panels and inverters go underground. A system that ceases to produce energy for 12 months is considered abandoned unless the owner gives the township evidence of intent to restart every six months, and removal and restoration are due within one year of abandonment. Utility-scale systems follow a separate special use track under Article XI.

Violations & Fines

Section 42-691(1) bars installing or operating a small-scale system except in compliance with the chapter. Zoning violations go to the building inspector under § 42-32(1): notice to cease, then if the owner fails to act diligently 14 days after notification, a second notice, notice to the township board and prosecution in court. Under § 2-156 a violation not designated a municipal civil infraction is a misdemeanor, fine up to $500.00 plus costs, or up to 90 days in jail.

Frequently Asked Questions

What must I submit to install solar panels in Fruitport Charter Township?
Section 42-691(1) requires equipment and unit renderings, elevation drawings, and site plans depicting the location and distances from lot lines and adjacent structures, in addition to all other application contents the chapter requires. The submission is made for review, and the system must comply with the chapter before it is installed or operated.
Do small solar collectors need approval?
Article X does not apply to collectors mounted on fences, poles, or on the ground with a collector surface area less than five square feet and less than five feet above the ground. Anything larger falls under the application and installation rules of §§ 42-691 to 42-693.
How big can a ground-mounted array be on a residential lot?
Residential ground-mounted systems are limited to one percent of the lot area up to 1,500 square feet of collector panels and a maximum height of six feet at full tilt. The lot must have at least 82,500 square feet, and only one ground-mounted unit is allowed per principal building.
What happens when a system stops producing power?
A system that ceases to produce energy continuously for 12 months is considered abandoned unless the responsible party gives the township substantial evidence of intent to reinstate it every six months after that. The responsible party must remove all equipment and restore the lot within one year of abandonment.

Sources & Official References

Other rules in Fruitport Charter Township

All Fruitport Charter Township rules

Compare Fruitport Charter Township to another location·View the Michigan solar energy overview

Get notified when Panel Permits in Fruitport Charter Township, MI changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.