Navajo County, AZ Solar Energy: Panel Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Allowed districts
A-General, Rural and Industrial only
Permit type
Special Use Permit and/or Development Agreement
Application fee
$600 plus $50 per acre
Fee cap
$25,000 maximum
Pre-filing step
Conceptual/pre-application meeting with the Department required
Buffering
Fencing, walls or landscaping required next to residential use

Summary

In unincorporated Navajo County, Arizona, a Solar Energy Generation Facility needs a Special Use Permit, Development Agreement, or both, and is allowed only in the A-General, Rural or Industrial zoning district. Section 1203 layers on setback, buffering and screening standards, and Section 1204 sets the permit fee at $600 plus $50 per acre, capped at $25,000.

These county ordinances apply to unincorporated areas of Navajo County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

Renewable Energy Generation facilities are allowed only in the A-General, Rural, and Industrial Zoning Districts, subject to either securing a Special Use Permit, Development Agreement, or both, and to the applicable site development standards set forth herein. ... ... 1. Setbacks. ... All Solar Energy Generation Facilities and structures must comply with setback, building height, and performance standards between zones for the zoning district in which the system is located, unless the County determines a modified setback is necessary to address impacts to existing adjacent uses. ... Fees for Special Use Permits for Renewable Energy Generation Facilities shall be $600.00 plus $50.00 per acre, with a fee cap of $25,000.00.

Full Breakdown

Sections 1201-1204 run the whole permit track for a solar project, from where it can sit to what it costs to file. 1 confines every Renewable Energy Generation Facility, solar included, to the A-General, Rural and Industrial zoning districts and requires a Special Use Permit, a Development Agreement, or both before construction, plus compliance with the site development standards in the rest of the Article; the section is explicit that it does not reach a project on state or federal land except where those agencies themselves require compliance with county zoning as part of their own approval.

a requires a conceptual and pre-application meeting with the Department, with the fire authority notified and invited. 2 allows a reduced setback if the project shares a property line with another approved solar facility or the affected owner records an irrevocable written consent. 3 requires buffering, fencing, walls or landscaping, wherever a solar facility adjoins residential development. 00 cap regardless of project size.

Violations & Fines

Building or operating a Solar Energy Generation Facility without the required Special Use Permit, or outside the A-General, Rural or Industrial districts, is a zoning violation a Code Enforcement Officer can cite under Section 2103. Section 1201.2.aa lets the Board of Supervisors suspend or revoke an issued SUP, in whole or part, after a public hearing if the holder fails to cure material noncompliance within 30 days of the Director's written notice.

Frequently Asked Questions

Where can a solar energy facility be built in unincorporated Navajo County?
Only in the A-General, Rural or Industrial zoning district. Section 1201.1 requires a Special Use Permit, a Development Agreement, or both, before any Solar Energy Generation Facility can be built, along with the site development standards set out in Article 12.
How much does the solar facility permit cost?
Section 1204 sets the fee for a Renewable Energy Generation Facility Special Use Permit at $600.00 plus $50.00 per acre of project area, with the total capped at $25,000.00 no matter how large the project is.
What setback does a solar project have to meet?
Section 1203.1 requires the setback, building-height and performance standards of the zoning district the system sits in, though Navajo County can require a larger setback to protect an existing adjacent use, or approve a smaller one if the neighboring owner signs an irrevocable recorded consent.
Does a solar facility next to homes need screening?
Yes. Section 1203.3 requires a Solar Energy Generation Facility that adjoins residential development to provide adequate screening, using fences, walls, landscaping or another structure the Planning and Development Services Department finds adequate.

Sources & Official References

Other rules in Navajo County

All Navajo County rules

Compare Navajo County to another location·View the Arizona solar energy overview

Get notified when Panel Permits in Navajo County, AZ changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.