Provo, UT Solar Energy: Panel Permits (2026)
Key Facts
- Governing law
- Provo City Code 12.03.080
- Review window
- 30 days to issue or deny
- Appeal deadline
- 30 days to Mayor after denial
- Residential fee (100-200A)
- $375.00 net metering hookup
- Commercial/residential fee (200-400A)
- $825.00 net metering hookup
- Under-25kW condition
- Must sign Net Metering Agreement
Summary
Provo runs its own electric utility, so home solar panels need a generation license from the Department, not a zoning permit. Applicants submit a license application, wait up to 30 days for a decision, and sign a Net Metering Agreement before connection.
Except as otherwise provided in Section 12.03.090, Provo City Code, this Section shall govern the generation and transmission of electric energy in Provo City by entities other than Provo City. Electric energy may not be generated or transmitted in Provo City without a license therefor... The applicant shall complete and submit the license application for consumer generation to the Department. The Department shall have thirty (30) days to review the license application and either issue a license or deny the license request. The Department's denial of a license application may be appealed to the Mayor within thirty (30) calendar days from the date written notice of denial is sent by the Department... A license for the generation of less than twenty-five (25) kW is subject to the following additional conditions: (i) The license is conditioned upon the licensee entering into the standard "Net Metering Agreement" between the licensee and the City; (ii) The licensee shall adhere to the current "Net Metering Standards" adopted by the Department.
Official source re-checked September 8, 2026: no newer edition of the code had been published (publisher’s edition: current through Ordinance 2026-17, passed June 9, 2026).
Full Breakdown
080, not just pulling a building permit. 080(1) makes generating or transmitting electric energy in the city unlawful without a license, and unauthorized generation can be grounds for disconnection at the Department Director's discretion. 080(2), the homeowner submits a license application for consumer generation to the Department, which then has thirty days to review it and either issue or deny the license; a denial can be appealed to the Mayor within thirty calendar days of the written notice. The Director may only issue the license if the installation will conform to all local, state and federal requirements, will not add technical or financial burden to the electric system beyond what is normal for properly designed distributed generation, and will not endanger the health, safety or welfare of residents or Department employees.
080(4)(e): the license is conditioned on signing the City's standard Net Metering Agreement and adhering to the Department's current Net Metering Standards. Noncompliance with those standards triggers immediate suspension and disconnection without advance notice, and the licensee bears the Department's actual enforcement costs. 00 for 200-400 amp commercial/residential service. 080(6) for everyone else, with unused credits lapsing at the February billing cycle each year. The Department may also inspect licensed generation facilities at any reasonable time and can impose conditions to protect system reliability.
Violations & Fines
Generating or transmitting electricity, including solar, without a Department license violates 12.03.080(1) and is grounds for disconnection from the city electrical system at the Director's discretion. A licensee who violates the Net Metering Standards faces immediate suspension and disconnection without advance notice, and must remedy the violation and pay the Department's actual enforcement costs before reinstatement or reconnection.
Frequently Asked Questions
Do I need a permit to put solar panels on my house in Provo?
What happens if the Department denies my solar license application?
How much does it cost to connect residential solar to Provo's grid?
Can Provo disconnect my solar system after it's licensed?
Sources & Official References
Other rules in Provo
Compare Provo to another location·View the Utah solar energy overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.