Key Facts

Application fee
$10,000 non-refundable, to Planning Commission
Permit fee
1% of total construction cost
Minimum lot size
20 aggregate acres
Setback from residence/church
500 feet
Decommissioning bond
At least $500,000
Permit expiration
3 years if construction not begun
Residential rooftop panels
Not covered by this article

Summary

Unincorporated Rapides Parish regulates permits for utility-scale solar farms, not for rooftop panels on a house or business. The Rapides Parish Planning Commission reviews every solar farm permit application under Police Jury Code Chapter 26, Article I, and the Police Jury holds final authority over approval, denial, and any transfer of the permit.

These county ordinances apply to unincorporated areas of Rapides Parish. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

This article has been promulgated by the Rapides Parish Police Jury in order to protect the health, safety, and welfare of the public and to provide for the orderly, planned, efficient, and healthy development of Rapides Parish (the "Parish"). This article grants the Parish and its Police Jury sole authority over all matters concerning a utility scale solar project facility ("solar farm") in the Parish. ... The provisions hereof apply to any and all solar farms constructed and/or operated in the Parish. This article allows both photovoltaic (PV) systems and photovoltaic-thermal (PV/T) USSPF systems, as defined herein, to be constructed and operated in the Parish, but shall not apply to solar collectors intended to provide electrical power generation for a single residential dwelling or commercial property. ... The up-front application fee for review shall be a non-refundable ten thousand dollars ($10,000.00) paid to the planning commission ... The solar farm permit fee shall be one percent of the total construction cost of the facility, plus any other applicable permit fees outlined in the Rapides Parish Police Jury and Rapides Area Planning Commission permit fee schedules.

Full Breakdown

The Rapides Parish Police Jury created the solar farm permitting scheme in Chapter 26, Article I (adopted by ordinance June 9, 2025) to cover any utility scale solar project facility, defined as a production facility that uses photovoltaic modules to convert solar energy into electricity delivered to a transmission system. The article expressly does not apply to a solar collector installed to power a single residential dwelling or commercial property, so a homeowner or business adding rooftop panels for its own use falls outside this permitting process.

For a qualifying solar farm, the applicant files a permit application with the Rapides Parish Planning Commission, which checks the application for completeness and gives the applicant 60 days to fix any deficiencies once notified in writing. The Planning Commission then recommends approval or denial to the Police Jury; construction cannot start until the Police Jury approves and the Planning Commission issues the permit. A facility must sit on at least 20 aggregate acres, keep panels back 100 feet from public roads and property lines (500 feet from an occupied residence, business, or place of worship), and stay under 16 feet for rotating racking or 18 feet for fixed panels.

Before construction begins, the owner must post a performance guarantee for decommissioning of no less than $500,000, even if salvage value would otherwise reduce that figure. The application fee is $10,000, non-refundable, and the permit fee itself equals one percent of total construction cost, due before the building permit issues. A permit lapses three years from issuance if construction has not begun, or four years if the facility has not reached substantial completion. Denials may be appealed to the Police Jury and, after that, to the district court within 30 days of the Police Jury's certified-mail decision.

Violations & Fines

Violating the article, or the permit conditions, lets the Police Jury withhold approvals, issue stop-work orders (including cutting Parish utility service), sue for an injunction, or prosecute the owner or operator as a misdemeanor under Code Section 1-13, punishable by up to $500 with each day of continued violation a separate offense. Unpaid penalties or repeat unremediated violations can trigger revocation of the solar farm permit itself.

Frequently Asked Questions

Does this permit process cover rooftop solar panels on my house?
No. Section 26-3 says the article applies to utility scale solar farms and does not apply to solar collectors intended to provide electrical power generation for a single residential dwelling or commercial property. Rooftop or small ground-mount systems sized for one home or business fall outside this chapter entirely.
Who reviews a solar farm permit application in Rapides Parish?
The Rapides Parish Planning Commission reviews every solar farm permit application, checks it for completeness, and can hire outside engineers or accountants at the applicant's expense. The Planning Commission then recommends approval or denial, but only the Police Jury can give final approval before construction may begin.
How much does a solar farm permit cost in Rapides Parish?
The upfront application review fee is a non-refundable $10,000 paid to the Planning Commission. Once approved, the solar farm permit fee itself is one percent of the total construction cost, plus any other fees in the Police Jury and Rapides Area Planning Commission fee schedules, due before the building permit issues.
What happens if a solar farm violates its permit?
The Police Jury can withhold permits, issue stop-work orders, cut Parish utility service, seek an injunction, or prosecute the violation as a misdemeanor under Code Section 1-13 with a fine up to $500 per day. Failure to pay or repeated unremediated violations can lead to revocation of the solar farm permit.

Sources & Official References

Other rules in Rapides Parish

All Rapides Parish rules

Compare Rapides Parish to another location·View the Louisiana solar energy overview

Get notified when Panel Permits in Rapides Parish, LA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.