Reno, NV Solar Energy: Panel Permits (2026)
Key Facts
- Screening
- Waived for solar panels
- Code compliance
- Must meet fire and building codes
- Utility notice
- Inform electric provider before install
- Setback height limit
- 6 feet max in side/rear yard
- Setback screening
- Solid fence as tall as panels
Summary
Reno treats solar panels as an alternative utility system allowed in every zoning district, exempt from the screening other systems need, but still subject to building- and fire-code review and utility notice.
In all zoning districts, all alternative utility systems, as defined in Section 18.09.302, shall comply with the following regulations:(1)Except for wind turbines and solar panels, alternative systems shall be screened from view or integrated into the design of the structure...(2)A system shall comply with applicable fire codes and building codes.(3)The applicant must provide satisfactory evidence that the electrical utility provider has been informed of the applicant's intent to install a system.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Administrative Code: Supplement 64 | Land Development Code: Supplement 5 Update 1).
Full Breakdown
Under Reno Municipal Code § 18.03.405(r), solar panel installations are alternative utility systems allowed in every zoning district. Unlike other alternative systems, solar panels are exempt from the requirement to be screened from view or integrated into the building design. Installations must still comply with applicable fire and building codes, and the applicant must show the electric utility provider has been informed of the plan to install the system before proceeding. Panels placed in a required side or rear yard setback may rise no more than six feet, per § 18.09.205(e)(5), and must be paired with a solid screen fence at least as tall as the panels along the property line.
Violations & Fines
Installing panels without meeting § 18.03.405(r) or exceeding the setback height allowance violates Title 18; the Administrator can issue a stop-work order and withhold building permits under § 18.01.504.
Frequently Asked Questions
Do I need to notify anyone before installing solar panels in Reno?
Can solar panels go in my setback in Reno?
Sources & Official References
Other rules in Reno
Compare Reno to another location·View the Nevada solar energy overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.