St. Martin Parish, LA Solar Energy: Panel Permits (2026)
Key Facts
- Permit needed before
- Construction, erection, establishment, expansion, or substantial alteration
- Solar farm threshold
- At least 50 kilowatts direct current
- Fee, 500 acres or less
- $1,000.00
- Fee, over 500 acres
- $1,000.00 plus $1.00 per acre over 500
- Administrative review
- Within 30 days of submittal
- Council presentation
- Within 90 days by the parish president
- Buffer setbacks
- 100 feet to road center, 150 feet from residence, 50 feet from property line
- Permit duration
- Expires one year after issuance unless construction commenced
Summary
Building a solar farm in unincorporated St. Martin Parish requires a parish permit under Section 20-402 before construction, expansion, or substantial alteration. A solar farm is a photovoltaic installation of at least 50 kilowatts direct current, the fee starts at $1,000.00, and the parish council gives final approval or denial by majority vote.
Solar farm means the use of land ... for the purpose of generating photovoltaic power which has a generation capacity of at least 50 kilowatts direct current (dc) or more when operating at maximum efficiency. "Solar farm" shall not be interpreted to mean one or more solar collectors intended to provide electrical power generation for a single residential dwelling or single commercial establishment. ... (a)Prior to the construction, erection, establishment, expansion, or substantially altering of a solar farm, a permit must be obtained by the developer from the Parish of St. Martin. Permits shall be issued only after the plan therefor has been approved as provided for in this chapter. ... the applicant shall pay a sum of $1,000.00 for any solar farm consisting of 500 acres or less. For a solar farm consisting of more than 500 acres, the fee shall be $1,000.00 plus an additional $1.00 for each acre in excess of 500 acres. ... The a ... dministrative review, to confirm the application is complete and meets design parameters set forth in this chapter, shall be completed within 30 days of application submittal.
Full Breakdown
Article XI of Chapter 20, adopted March 7, 2023 as Ord. No. 23-03-1386-OR, regulates the licensure, operations, and siting of solar farms within the unincorporated areas of St. Martin Parish. Section 20-401 defines a solar farm as a use of land with photovoltaic generation capacity of at least 50 kilowatts direct current. One or more collectors serving a single residential dwelling or a single commercial establishment are not a solar farm, so this permit does not reach a system on one home.
The application goes to the parish supervisor of permits. It must include a site plan showing all property in the project, all access roads, and the buffer zones, plus a drainage study, environmental study, maintenance plan, and traffic plan. Before filing, the applicant holds at least one public meeting under the planning and zoning director or a designee, with notice published in the official journal at least ten days and no more than 30 days beforehand and posted on the parish government website. The applicant pays the publication costs.
The fee is $1,000.00 for a solar farm of 500 acres or less, and $1,000.00 plus $1.00 for each acre over 500 for a larger one, measured on the entire project including buffer zones and access roads. The permits supervisor checks completeness, the director of public works reviews next, and the parish president finishes administrative review within 30 days of submittal. The president then presents the plans and studies to the parish council within 90 days for approval or denial, decided by majority vote of the entire council.
A denial comes with a written statement of reasons, and the applicant has 30 days to submit more information or an amended plan. A final denial can be appealed to the parish president, who acts within 14 days, and then to the council within 90 days of the president's decision. A permit expires one year after issuance unless construction has commenced or an extension is requested at least 30 days before expiration. Section 20-411 classifies every solar farm as I-1 (Light Industrial) under the Zoning Ordinance, reverting to the original class on decommissioning.
Violations & Fines
Under Section 20-402(i), the permit gives St. Martin Parish Government standing to enforce every obligation by any means allowed by law, including suits for damages or injunctions in the 16th Judicial Court. Section 20-410 adds a $500.00 penalty for each day a maintenance deficiency stays unremedied, starting 30 days after written notice. Section 20-406 allows revocation of the permit for buffer zone violations. Cessation of operations beyond 180 days in a calendar year triggers decommissioning and termination of the permit under Section 20-408.
Frequently Asked Questions
Does a rooftop system on one home need this solar farm permit?
How long does the parish take to decide a solar farm permit?
What setbacks does a solar farm in St. Martin Parish need?
What happens when a solar farm stops operating?
Sources & Official References
Other rules in St. Martin Parish
Compare St. Martin Parish to another location·View the Louisiana solar energy overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.