West New York, NJ Solar Energy: Panel Permits (2026)
Key Facts
- 1 to 25 panels, microinverters, optimizers
- $80 (§ 161-2B(3))
- Each additional 25 units
- $35
- Minimum electrical permit fee
- $70
- Plan review
- Nonrefundable 20% of the permit fee
- Work without a permit
- Added fee of 15% of permit fee, $50 minimum
- Fines under § 161-2L
- Up to $100 first offense; $50 to $500 repeat
Summary
In the Town of West New York, New Jersey, a photovoltaic system is priced in the electrical fee schedule of § 161-2: $80 for 1 to 25 panels, microinverters and optimizers, plus $35 for each additional 25 units. Fees are collected before plan review or permit issuance, and the minimum electrical permit fee is $70.
All fees required for plan review and the issuance of any permit or certificate shall be collected prior to the review or the issuance of the permit or certificate. ... (a) The minimum electrical permit fee shall be $70. (b) The fee for all fixtures or devices shall be as follows: Fixture/Device Fee ... Photovoltaic system: 1 to 25 panels, microinverters, optimizers $80 Each additional 25 units $35 1 to 10 kw $60 11 to 50 kw $90 51 to 100 kw $120 Greater than 100 kw $576
Full Breakdown
The only place the Town Code names a photovoltaic system is the electrical fee schedule in § 161-2B(3), part of the West New York Building Department and Code Enforcement Fee Schedule. The fee for fixtures and devices lists the photovoltaic system as $80 for 1 to 25 panels, microinverters and optimizers, then $35 for each additional 25 units. The same listing continues with kw tiers: $60 for 1 to 10 kw, $90 for 11 to 50 kw, $120 for 51 to 100 kw and $576 for greater than 100 kw. The minimum electrical permit fee is $70.
Section 161-2A requires all fees for plan review and the issuance of any permit or certificate to be collected before the review or issuance, and a copy of the schedule is posted in the Central Permit Office. Plan review is a nonrefundable 20% of the permit fee. The Construction Code Official calculates fees under the State Uniform Construction Code, and if that code requires a greater fee than the schedule, the greater fee is due. Payment to the Code Enforcement Department is by money order, certified check or cashier's check.
The permit is issued through the Code Enforcement Department created by § 161-1, which includes an Electrical Subcode Official and a Fire Protection Subcode Official and does business with the public at one office location. A lapsed permit can be reinstated for 25% of the initial permit fee if the application is made within one year of lapse, and for 100% of the initial fee after that.
Starting work without a required permit adds a fee of 15% of the permit fee, with a $50 minimum. A person who knowingly or intentionally fails to obtain a required permit, who keeps working after a written stop-work notice, or who repeatedly builds without permits receives a violation from the Construction Code Official, returnable in the Municipal Court of West New York.
Violations & Fines
Under § 161-2I through K, the Construction Code Official issues a violation, returnable in the Municipal Court of West New York, for knowingly failing to obtain a required permit, for continuing work after a written notice to cease until a permit is issued, and for a pattern of building without permits. Section 161-2L sets a fine not to exceed $100 for a first offense and, for second or repeated offenses, a minimum of $50 and a maximum of $500 for each separate offense, in addition to Uniform Construction Code penalties.
Frequently Asked Questions
How much is a solar panel permit fee in the Town of West New York?
When are the fees paid?
What if solar work starts without a permit?
Does the Town Code set solar zoning standards?
Sources & Official References
Other rules in West New York
Compare West New York to another location·View the New Jersey solar energy overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.