Nebraska Construction Stormwater and Erosion Control Permit Rules

Some RestrictionsApplies statewide across Nebraska (2026)

Key Facts

Governing statute
Neb. Rev. Stat. 81-1506(2)(a)
Permit trigger
Land disturbance one acre or more
Notice of Intent
File 7 days before grading
Required plan
Storm Water Pollution Prevention Plan
Maximum penalty
$10,000 per day, court-assessed
Last verified: July 31, 2026

Summary

Nebraska Revised Statute 81-1506(2)(a) makes it unlawful to discharge pollutants into waters of the state without an NPDES permit. Construction disturbing one acre or more must obtain the state Construction Storm Water general permit and run a plan controlling erosion and sediment runoff.

(2) It shall be unlawful for any person to: ... (a) Discharge any pollutant into waters of the state without obtaining a permit as required by the National Pollutant Discharge Elimination System created by the Clean Water Act, as amended, 33 U.S.C. 1251 et seq.

Full Breakdown

Under the Nebraska Environmental Protection Act, section 81-1506(2)(a) prohibits discharging any pollutant into waters of the state without a permit issued under the National Pollutant Discharge Elimination System. The Nebraska Department of Environment and Energy administers this through its Construction Storm Water general permit (NER210000). Land-disturbing activity of one acre or more, or smaller sites within a common plan of development, must file a Notice of Intent with the department at least seven days before clearing and grading, and maintain a Storm Water Pollution Prevention Plan detailing silt fences, sediment traps, seeding, and stabilization measures to keep sediment out of downstream waters.

Violations & Penalties

Discharging construction stormwater without permit coverage, or failing to implement the required pollution prevention plan, violates section 81-1506. Under section 81-1508.02 a court may impose civil penalties of up to ten thousand dollars per day of violation.

Frequently Asked Questions

When does a Nebraska construction project need a stormwater permit?
When land disturbance reaches one acre or more, or is part of a larger common plan of development. File the Department of Environment and Energy Construction Storm Water Notice of Intent at least seven days before grading begins.
What is the penalty for discharging construction runoff without a permit?
Section 81-1506 makes it unlawful. Under section 81-1508.02, a court may impose civil penalties of up to ten thousand dollars per day of violation, weighing the extent and any economic benefit from noncompliance.