Key Facts

ADU total impact fee
$2,401.00
Transportation component
$575.00
Schools component
$593.00
Parks component
$403.00
When fee is due
At building permit issuance
Refund window
10 years, 2% annual interest

Summary

Citrus County charges a $2,401.00 impact fee on every new accessory dwelling unit, due at the time a building permit or equivalent approval is issued. The fee is broken into eight components under Exhibit A of Chapter 54, covering transportation, schools, parks, library, fire, EMS, law enforcement and public buildings.

These county ordinances apply to unincorporated areas of Citrus County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

Land Use Unit Transp. (50%) Schools (50%) Parks Library Fire EMS Law Enf. Public Bldgs. Total Accessory Dwelling Unit Dwelling $575.00 $593.00 $403.00 $188.00 $170.00 $38.00 $253.00 $181.00 $2,401.00

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 76).

Full Breakdown

Sec. 54-4(a)(1) obligates anyone commencing impact-generating land development, unless exempted under Sec. 54-4(a)(2), to pay the fee set by the schedule in Exhibit A at the time a building permit is issued. 00 charged for a new single-family detached home. Sec. 54-4(a)(2) exempts alterations that add no dwelling units and generate no additional trips or facility demand, along with several other categories such as school and charter-school facilities and additions that create no new unit. Sec. 54-9 lets an owner recover fees not spent within ten years of the building permit date, with 2 percent annual interest, through a refund review by the department of growth management and the department of management and budget.

Fees are held in a dedicated Citrus County Impact Fee Trust Fund under Sec. 54-8, divided into per-district and per-facility trust accounts, and can only fund capacity-adding capital projects, not operations or existing deficiencies.

Violations & Fines

The chapter does not set out a separate fine; failure to pay the impact fee before the triggering permit or approval event under Sec. 54-4(a)(1) blocks issuance of that building permit, development order or certificate needed to proceed with construction of the accessory dwelling unit.

Frequently Asked Questions

How much is the impact fee for an accessory dwelling unit in Citrus County?
Exhibit A to Chapter 54 sets the total at $2,401.00, split across transportation ($575.00), schools ($593.00), parks ($403.00), library ($188.00), fire ($170.00), EMS ($38.00), law enforcement ($253.00) and public buildings ($181.00).
When do I have to pay the ADU impact fee?
Sec. 54-4(a)(1) requires payment when the building permit is issued, or at the earliest of several listed triggering events, such as first use of the unit, if no conventional building permit is required for the project.
Can I get the fee back if the county never spends it?
Yes. Sec. 54-9 requires a refund to the current property owner, with 2 percent annual interest, if the fee has not been spent within ten years of the building permit date, unless the board extends that window by resolution.

Sources & Official References

Other rules in Citrus County

All Citrus County rules

Florida rules heatmap·Compare Citrus County to another location·View the Florida accessory structures overview

Get notified when ADU Impact Fees in Citrus County, FL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.