Bakersfield, CA Building Safety: Building Permits (2026)
Key Facts
- Applicability standard
- BMC § 15.04.050
- Adoption/scope of permitting
- BMC § 15.05.010 (2025 CBC)
- Suspension trigger
- 180+ days of inactivity
- New permit deadline
- 30 days from director's notice
- Demolition deadline
- 60 days from director's notice
Summary
Bakersfield's buildings and construction code, adopted at § 15.04.050, reaches new building construction and any new mechanical, plumbing, electrical or sign system; leave a permitted project stalled 180 days and § 15.04.110 forces you to re-permit within 30 days or demolish within 60.
The buildings and construction code applies to new building construction and to the installation of new mechanical, plumbing, electrical and sign systems as well as to existing construction and to existing mechanical, plumbing, electrical and sign systems to the extent specifically defined by the codes adopted by reference into this title.
Official source re-checked September 8, 2026: no newer edition of the code had been published (publisher’s edition: current through Ordinance 5221, passed July 15, 2026).
Full Breakdown
Municipal Code § 15.05.010 adopts the 2025 California Building Code "for the purpose of regulating the erection, construction, enlargement, alteration, repair, moving, removal, demolition, conversion, occupancy, use, height and maintenance of all structures and certain equipment therein specifically regulated within the incorporated limits of the city, issuance of permits and the collection of fees thereof." Section 15.04.050 narrows what that reach means in practice: the buildings and construction code "applies to new building construction and to the installation of new mechanical, plumbing, electrical and sign systems as well as to existing construction and to existing mechanical, plumbing, electrical and sign systems to the extent specifically defined by the codes adopted by reference into this title." Once a permit issues, it doesn't last indefinitely: § 15.04.110 gives the building director authority to act when work "has been suspended or abandoned for a period of one hundred eighty or more days." The director must give the property owner written notice to either obtain a new permit and diligently complete the work, or demolish and remove it.
The owner then has thirty days from that notice to pull a new permit and get moving, or must instead obtain a demolition permit and remove the structure or project within sixty days of the notice date, there is no third option. Fee payment for any of these permits routes through the Master Fee Schedule under § 15.05.050, and the building director keeps a permanent transaction record under § 15.04.090. Read together, these sections establish that virtually any new construction, system installation, enlargement or alteration in the city requires a permit issued under Title 15, and that an issued permit carries an active-work expectation enforced by the 180-day/30-day/60-day timeline in § 15.04.110.
Violations & Fines
Building without a required permit, or letting a permitted project sit stalled past the notice deadlines in § 15.04.110, is a Title 15 violation punishable under the general penalty at § 1.40.010: up to $250 for a repeat infraction or a misdemeanor carrying up to $1,000 or six months in county jail, with each day of continued noncompliance a separate offense.
Frequently Asked Questions
What construction requires a permit in Bakersfield?
What happens if I stop work on a permitted project?
Can I let an old permit just sit unused?
Who administers Bakersfield's building permit system?
Sources & Official References
Other rules in Bakersfield
California rules heatmap·Compare Bakersfield to another location·View the California building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Building Permits in Nearby Cities
How other cities in Kern County handle building permits.