Bakersfield, CA Building Safety: Building Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified August 2026

Key Facts

Applicability standard
BMC § 15.04.050
Adoption/scope of permitting
BMC § 15.05.010 (2025 CBC)
Suspension trigger
180+ days of inactivity
New permit deadline
30 days from director's notice
Demolition deadline
60 days from director's notice

Summary

Bakersfield's buildings and construction code, adopted at § 15.04.050, reaches new building construction and any new mechanical, plumbing, electrical or sign system; leave a permitted project stalled 180 days and § 15.04.110 forces you to re-permit within 30 days or demolish within 60.

The buildings and construction code applies to new building construction and to the installation of new mechanical, plumbing, electrical and sign systems as well as to existing construction and to existing mechanical, plumbing, electrical and sign systems to the extent specifically defined by the codes adopted by reference into this title.

View official code

Official source re-checked September 8, 2026: no newer edition of the code had been published (publisher’s edition: current through Ordinance 5221, passed July 15, 2026).

Full Breakdown

" The director must give the property owner written notice to either obtain a new permit and diligently complete the work, or demolish and remove it. The owner then has thirty days from that notice to pull a new permit and get moving, or must instead obtain a demolition permit and remove the structure or project within sixty days of the notice date, there is no third option. 090. 110.

Violations & Fines

Building without a required permit, or letting a permitted project sit stalled past the notice deadlines in § 15.04.110, is a Title 15 violation punishable under the general penalty at § 1.40.010: up to $250 for a repeat infraction or a misdemeanor carrying up to $1,000 or six months in county jail, with each day of continued noncompliance a separate offense.

Frequently Asked Questions

What construction requires a permit in Bakersfield?
Section 15.04.050 applies the buildings and construction code to all new building construction and to installation of new mechanical, plumbing, electrical or sign systems, as well as to existing construction to the extent the adopted California codes specifically cover it.
What happens if I stop work on a permitted project?
If the building director finds work suspended or abandoned for 180 or more days, § 15.04.110 requires written notice giving the owner 30 days to obtain a new permit and resume work, or 60 days to instead obtain a demolition permit and remove the structure.
Can I let an old permit just sit unused?
No. Once the building director issues the 180-day notice under § 15.04.110, the owner must choose one of the two paths, re-permit and complete, or demolish, there is no provision allowing indefinite inactivity after notice.
Who administers Bakersfield's building permit system?
The building director, per § 15.04.080 and § 15.04.090, enforces Title 15, keeps a permanent record of every department transaction, and forwards permit fees to the finance director for deposit in the development services fund.

Sources & Official References

Other rules in Bakersfield

All Bakersfield rules

California rules heatmap·Compare Bakersfield to another location·View the California building safety overview

Get notified when Building Permits in Bakersfield, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Permits in Nearby Cities

How other cities in Kern County handle building permits.

Ridgecrest, CA
Some Restrictions