Key Facts

Citation
§ 54-801, building permit applicability
Issued by
zoning administrator or town inspector
Permit lapses
after 1 year if unstarted
Coverage
towns that adopted county zoning
Excludes
Appleton, Kaukauna, other incorporated cities

Summary

Outagamie County requires a building permit from the zoning administrator or town building inspector before any structure is built, altered, moved or enlarged, but only in unincorporated towns that adopted the county's zoning chapter.

City-specific rules exist: Little Chute, and Appleton have their own building permits rules that differ from Outagamie County's county-level regulations. If you live in one of those cities, check the city-specific page instead.

No building or structure, except signs exempt from the provisions of this chapter, shall be erected, constructed, reconstructed, altered, moved or enlarged until a building permit has been obtained from the administrator or town building inspector.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 26).

Full Breakdown

Section 54-801 of the Outagamie County Code bars erecting, constructing, reconstructing, altering, moving or enlarging any building or structure, except exempt signs, until a building permit is obtained from the county zoning administrator or the local town building inspector. The requirement flows from chapter 54's zoning provisions, which under Wis. Stat. § 59.69 take effect only in towns whose boards adopted county zoning; a permit lapses if construction hasn't substantially begun within one year of issuance, per section 54-805. Incorporated cities and villages, including Appleton, Kaukauna and Kimberly, issue building permits under their own municipal codes, not this chapter.

Violations & Fines

Building without a permit, or building outside the approved plans, is a violation of chapter 54; the county can revoke a permit issued in error and pursue enforcement action for noncompliant construction.

Frequently Asked Questions

Do I need a county permit to build in Appleton or Kaukauna?
No. Section 54-801 only governs unincorporated towns that adopted Outagamie County zoning; Appleton, Kaukauna and other incorporated cities issue their own building permits.
How long is an Outagamie County building permit valid?
It lapses automatically if substantial construction hasn't started within one year of issuance, under section 54-805.

Sources & Official References

Other rules in Outagamie County

All Outagamie County rules

Compare Outagamie County to another location·View the Wisconsin building safety overview

Get notified when Building Permits in Outagamie County, WI changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Permits in Cities Across Outagamie County