Key Facts

New building occupancy bar
No occupancy before CO issued
TCO initial term
30 days
TCO extension
One additional 30 days
Conditional CO cap
One year
Commercial TCO finals required
6 (incl. engineering final)
Citation
El Paso City Code § 18.02.111.1

Summary

A new building in El Paso cannot be occupied, and no occupancy change made, until the building official issues a certificate of occupancy under City Code § 18.02.111.1, which requires passing every required inspection first. A Temporary Certificate of Occupancy is available for incomplete buildings for 30 days, extendable once, once life-safety systems pass final inspection.

18.02.111.1 - New building certificate of occupancy. A new building shall not be occupied or a change made in the occupancy, nature or use of a building or part of a building until the building official has issued a certificate of occupancy. The certificate shall not be issued until the building has passed all required inspections, is in compliance with the technical codes and other applicable laws and ordinances and is released by the building official and the applicant has paid the established fee.

Full Breakdown

2: an owner applies, supplies the data needed to show compliance for the intended occupancy, and the building official may require detailed drawings or a general inspection before issuing the certificate and collecting the fee. 5 authorizes a Temporary Certificate of Occupancy once the building passes its life-safety and service-system finals - for a commercial TCO that means "[e]ngineering final, electrical final, fire final, mechanical final, plumbing final, building final"; a residential TCO drops the engineering final. 7 authorizes a certificate of completion for non-occupiable systems work like fire protection or mechanical installations that pass final inspection with no violations found. These sections were adopted by Ord. No. 019528 on August 1, 2023.

Violations & Fines

Occupying or changing the use of a building before the building official issues the certificate of occupancy violates § 18.02.111.1 outright; a Temporary Certificate of Occupancy that lapses after its 30-day term (or single 30-day extension) without a final certificate leaves the space occupied without authorization until the required finals are passed and the fee is paid.

Frequently Asked Questions

Can I move into a new building before it's inspected?
No. Section 18.02.111.1 bars occupancy of a new building, or any occupancy change, until the building official issues a certificate of occupancy, which itself cannot be issued until the building has passed every required inspection and the fee is paid.
How long does a Temporary Certificate of Occupancy last in El Paso?
Section 18.02.111.5 makes a TCO valid for thirty days, with one 30-day extension available on written request and payment of the established fee, but only after the building passes its life-safety and service-system final inspections.
What inspections does a commercial TCO require?
Section 18.02.111.5 lists engineering final, electrical final, fire final, mechanical final, plumbing final, and building final as the required inspections before a commercial Temporary Certificate of Occupancy can be issued.
Can an existing building get a certificate of occupancy for a new use?
Yes. Section 18.02.111.2 lets an owner apply for an existing-building certificate of occupancy by supplying data showing compliance for the intended occupancy, subject to the building official's review, inspection, and the established fee.

Sources & Official References

Other rules in El Paso

All El Paso rules

Texas rules heatmap·Compare El Paso to another location·View the Texas building safety overview

Get notified when Building Permits in El Paso, TX changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.