Key Facts

Permit expires
Twelve months after issuance if no substantial work starts
First extension
One twelve-month extension, fee up to $100
Request deadline
At least ten days before expiration
Work suspended
More than six months invalidates plan approval
Work without permit
Permit fees doubled under Section 1317.07
Issuing office
Elyria Building Department

Summary

In the City of Elyria, Ohio, a building permit issued by the Building Department expires twelve months after issuance if no substantial work starts on the site. Section 1317.10 allows one twelve-month extension for a fee of not more than $100, and work stalled for more than six months invalidates plan approval.

(a) A permit issued by the Building Department shall expire twelve months after its issuance if no substantial work is commenced upon the site of the project for which the permit was issued. (b) One extension shall be granted for an additional twelve-month period if requested by the owner at least ten days in advance of the expiration of the permit and upon payment of a fee of not more than one hundred dollars ($100.00). (c) If, in the course of construction, work is delayed or suspended for more than six months, the approval of plans, drawings, specifications or data is invalid. Two extensions shall be granted for six months each if requested by the owner at least ten days in advance of the expiration of the permit and upon payment of a fee, for each extension, of not more than one hundred dollars ($100.00).

Full Breakdown

Section 1317.10 of the Elyria Codified Ordinances controls how long a building permit lasts. A permit issued by the Building Department expires twelve months after issuance if no substantial work is commenced upon the site of the project. One extension of twelve months is granted if the owner asks at least ten days before the permit expires and pays a fee of not more than one hundred dollars ($100.00). Once construction is under way, a delay or suspension of more than six months makes the approval of plans, drawings, specifications or data invalid. Two extensions of six months each are granted if the owner asks at least ten days before expiration and pays, for each extension, a fee of not more than $100.00.

Other sections of Chapter 1317 surround that rule. Permit fees are set by Section 109.13 of the Administrative Code (Section 1317.01). Section 1317.06 defines "repairs" as the replacement of existing material with the same kind of material, excluding work that would affect structural safety or a vital element of an elevator, plumbing or gas piping, wiring or heating installation. The chapter itself does not list every job that needs a permit. Section 1317.08 requires a Certificate of Occupancy when a change in use or occupancy reclassifies a building, and Section 1317.09 requires a Certificate of Approval stating that all work requiring inspection is approved by the Building Department. Section 1317.12 waives permit fees for renovation of City facilities for compliance with the Americans With Disabilities Act.

The Building Department is a subdepartment of the Department of Safety-Service, administered by the Building Inspector and deputy inspectors (Section 1313.01), and the Building Inspector enforces the Building Code (Section 1313.02). Section 1301.01 adopts the 2017 Ohio Basic Building Code, and Section 1304.01 adopts the 2019 Residential Code of Ohio for one, two and three family dwellings.

Violations & Fines

Starting permit-required work without a permit doubles the permit fee under Section 1317.07 when the person knew or should have known a permit was needed, and paying the double fee does not excuse compliance. Section 1313.99 sets a fine of not more than $300, imprisonment of not more than ninety days, or both, with each day a separate offense. Failing to cease work after a stop work order is declared a public nuisance by Section 1301.04(f).

Frequently Asked Questions

How long is an Elyria building permit good for?
Section 1317.10(a) says a permit issued by the Building Department expires twelve months after issuance if no substantial work is commenced upon the site of the project. One extension of twelve months is available, so the owner needs to ask at least ten days ahead of the expiration date and pay a fee of not more than $100.00.
What if construction stops partway through a project in Elyria?
Under Section 1317.10(c), work that is delayed or suspended for more than six months makes the approval of plans, drawings, specifications or data invalid. The owner can obtain two extensions of six months each by asking at least ten days before the permit expires and paying a fee of not more than $100.00 for each extension.
What does Elyria charge if work starts without a permit?
Section 1317.07 doubles the permit fees when work requiring a permit is commenced without one by a person who had knowledge, or should have had knowledge, that a permit was required. The double fee does not relieve anyone from fully complying with the rules for building, plumbing, wiring, heating and cooling in the City.
Where can I appeal a Building Department decision in Elyria?
Section 1315.07 lets any person affected by a decision of the Chief Building Official, or a notice or order under the Building Code, appeal to the Board of Building Standards and Appeals. The written application must be filed within twenty days after the decision, notice or order was served. Condemnation and demolition orders follow Chapter 1391 instead.

Sources & Official References

Other rules in Elyria

All Elyria rules

Compare Elyria to another location·View the Ohio building safety overview

Get notified when Building Permits in Elyria, OH changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.