Skip to main content
CityRuleLookup

Hanover County, VA Building Safety: Building Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permit required before
erecting, altering, moving, enlarging any building
Plan review fee
20% of building permit fee
Worship building fee exemption
no permit fee charged
Zoning penalty, first ticket
$200 civil penalty
Zoning penalty, repeat ticket
$500 civil penalty
Criminal misdemeanor fine range
$10 to $1,000

Summary

In Hanover County outside the Town of Ashland, no building may be erected, altered, moved, converted, extended or enlarged without a building permit under the Zoning Ordinance (chapter 26) and the building code fee requirements of section 6-19. Permit applications must include a plat, and fees set by the board of supervisors must be paid before work begins.

These county ordinances apply to unincorporated areas of Hanover County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

No building shall be erected, constructed, altered, moved, converted, extended, or enlarged, without the owner or owners first having obtained a building permit. Such permit shall require conformity with the provisions of this Ordinance. ... All applications for building permits shall be accompanied by a drawing or plat in duplicate or as required by the zoning administrator showing, with dimensions, the lot lines, the building or buildings, the location of buildings on the lot and such other information as may be necessary to provide for the enforcement of these regulations, including, if necessary, a boundary survey and a staking of the lot by a competent surveyor and complete construction plans.

Full Breakdown

Hanover County Code section 26-342 flatly bars erecting, constructing, altering, moving, converting, extending or enlarging any building without the owner first obtaining a building permit that conforms to the zoning ordinance. Section 26-344 requires every permit application to be accompanied by a drawing or plat, in duplicate or as the zoning administrator requires, showing lot lines, building locations and dimensions, and, when necessary, a boundary survey by a licensed surveyor and complete construction plans; the zoning administrator keeps the original on file and a duplicate must stay at the building site throughout construction.

On the building-code side, section 6-19 bars issuing any permit for new construction, alteration, removal, demolition or other building work under the Virginia Uniform Statewide Building Code until the fees the board of supervisors has set are paid, and the building official can assess additional fees if plans show the original payment fell short. No fee applies to permits for buildings used as a place of worship. An applicant can get plans reviewed before formally applying for a permit, for buildings other than one- and two-family homes, by paying a nonrefundable fee equal to 20 percent of the eventual building permit fee, which is applied toward that permit fee if the application follows within 12 months.

If a permit is revoked or a project is abandoned, the county refunds the portion of fees tied to uncompleted work. The building official, established under section 6-17, administers and enforces the Uniform Statewide Building Code, while the zoning administrator enforces the zoning ordinance permit requirement and can refuse to issue a permit for any building or use that would violate the zoning chapter under section 26-341.

Violations & Fines

A zoning ordinance permit violation under section 26-347 draws a $200 civil penalty for the first ticket and $500 for each additional ticket from the same facts, capped at $5,000 total before the county can pursue a criminal misdemeanor under section 26-349, punishable by a fine of $10 to $1,000 per offense, or more for continued noncompliance.

Frequently Asked Questions

Do I need a permit to add onto my house in Hanover County?
Yes. Section 26-342 requires a building permit before any building is erected, altered, moved, converted, extended or enlarged, and the permit must conform to the zoning ordinance. You also need to pay the building code permit fee under section 6-19 before work starts.
What do I need to submit with a building permit application?
Section 26-344 requires a plat or drawing, in duplicate, showing the lot lines and building locations and dimensions, plus complete construction plans and, when necessary, a boundary survey by a licensed surveyor. A copy must stay at the building site during construction.
Are any buildings exempt from Hanover County's permit fees?
Yes. Section 6-19(c) waives the building permit fee for permits issued to construct buildings designed for and used to house religious assemblies as a place of worship, though the underlying building permit itself under section 26-342 is still required before construction starts.

Sources & Official References

Other rules in Hanover County

All Hanover County rules

Compare Hanover County to another location·View the Virginia building safety overview

Get notified when Building Permits in Hanover County, VA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.