Cobb County, GA Building Safety: Building Permits (2026)
Key Facts
- Permit required for
- building, electrical, mechanical, plumbing, gas work
- Issuing office
- Development and Inspections Division, Community Development Agency
- Residential remodeling permit expires
- 180 days, or 60 days idle
- All other residential permits expire
- 1 year from issuance regardless of progress
- Non-remodeling permits expire
- 180 days uncommenced, or 180 days idle
- Extensions available
- up to 180 days each, building official's discretion
- Scope
- unincorporated Cobb County only
Summary
Cobb County requires a permit before any building, electrical, mechanical, plumbing, or gas work begins on unincorporated property, issued by the Development and Inspections Division of the Community Development Agency. Skip the permit and even a passed after-the-fact inspection won't erase the violation. Permits also expire: residential remodeling jobs get 180 days, other permits 180 days to start work, and all residential permits die outright after one year.
Any contractor, owner or authorized representative, doing any electrical, mechanical, plumbing, gas or building construction, shall obtain a permit for same through proper application to the development and inspections division of the community development agency of Cobb County, Georgia, before performing such work. If work requiring a permit is started without proper permitting, an after-the-fact permit may not be granted if the work is not compliant with all other federal, state and local codes and ordinances. Regardless whether or not an after-the-fact permit is obtainable the contractor and the owner will be in violation of this ordinance if work is started without proper permitting as required. ... Notwithstanding any other provision contained within the specific building codes adopted by Cobb County, residential remodeling permits or any permit for the remodeling of a residential house shall expire after 180 days. Furthermore, residential remodeling permits shall expire if work is discontinued for a period of 60 days.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 53).
Full Breakdown
Cobb County Code § 18-27(a) requires any contractor, owner, or authorized representative doing electrical, mechanical, plumbing, gas, or building construction work in unincorporated Cobb County to get a permit through the Development and Inspections Division of the Community Development Agency before the work starts. Start without one and the code is explicit: if the finished work does not comply with every applicable federal, state, and local code, the county can refuse to issue an after-the-fact permit, and the contractor and owner are already in violation the moment work began, regardless of whether an after-the-fact permit is later granted.
Expiration rules split by permit type. Under § 18-27(b), a residential remodeling permit expires after 180 days, and separately expires if work sits idle for 60 straight days, meaning no passing electrical, mechanical, plumbing, gas, or building inspection gets recorded in any 60-day window. The building official can grant one or more extensions of up to 180 days each if the remodeling is moving along efficiently and not dragging down the surrounding neighborhood. Every other residential permit, remodel or not, expires exactly one year from issuance no matter how much progress has been made.
Under § 18-27(c), non-remodeling permits become invalid if work is not commenced within 180 days of issuance, or is discontinued, suspended, or abandoned for 180 days after commencement, again measured by the absence of a passing inspection in any 180-day stretch. The building official may grant extensions of up to 180 days each, but only on a showing of justifiable cause.
Section 18-27(d) folds in stormwater compliance: every building permit must list the certification number of the company or individual responsible for designing, installing, and maintaining erosion and sediment control devices on the site, and since December 31, 2006, anyone involved in designing, reviewing, permitting, constructing, monitoring, or inspecting land-disturbing activity must hold the education and training certification the state commission requires under O.C.G.A. § 12-7-20.
Violations & Fines
Starting regulated work without a permit puts the contractor and the property owner in violation of § 18-27(a) immediately, and a passing after-the-fact inspection doesn't retroactively fix that exposure. General code violations run through § 1-10: a magistrate-court conviction carries the maximum fine and jail or probation term set by O.C.G.A. § 15-10-60, and the county can revoke or suspend the permit or license on top of any fine. Continuing violations count as a nuisance the county can shut down through injunctive relief.
Frequently Asked Questions
Do I need a permit for a Cobb County home remodel?
How long is a Cobb County residential remodeling permit good for?
What happens if I start work in Cobb County without a permit?
Does a Cobb County building permit ever expire outright regardless of progress?
Sources & Official References
Other rules in Cobb County
Compare Cobb County to another location·View the Georgia building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.