Key Facts

Adopted codes
Georgia State Minimum Standard Codes (§ 18-31)
Permit trigger
Regulated construction, alteration, repair, demolition
Application lapse
Deemed abandoned after 6 months, no permit
Permit validity
6 months from last passed inspection
Late-start penalty
100% of permit fee, plus the fee itself
Enforcing official
Acworth Building Official

Summary

Acworth enforces Georgia's state minimum construction codes rather than writing its own, and Section 18-56 requires a permit from the building official before anyone builds, alters, repairs, moves, or demolishes a building or structure, or installs a regulated electrical, gas, mechanical or plumbing system.

Sec. 18-31. - Adopted. (a)The following codes, the latest edition as adopted and amended by the state department of community affairs, shall be enforced by the city:(1)Georgia State Minimum Standard Building Code(2)Georgia State Minimum Standard One and Two Family Dwelling Code ... Sec. 18-56. - Permits. (a)Permit application.(1)Permitting required. When required, any owner, authorized agent, or contractor who desires to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure, or to erect, install, enlarge, alter, repair, remove, convert, or replace any sign, electrical, gas, mechanical, or plumbing system, the installation of which is regulated by the construction codes, or to cause any such work to be done, shall first make application to the building official and obtain the required permit for the work.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 27).

Full Breakdown

Section 18-31 adopts the Georgia State Minimum Standard Building, One- and Two-Family Dwelling, Fire, Plumbing, Mechanical, Gas, Electrical and Energy Codes, plus the 2006 International Property Maintenance Code as amended locally, as the construction codes the city enforces; there's no separate Acworth-authored building code underneath them. Section 18-56(a)(1) sets the trigger for a permit: any owner, agent or contractor who wants to construct, enlarge, alter, repair, move, demolish or change the occupancy of a building or structure, or to erect, install, alter, repair, remove, convert or replace a regulated sign, electrical, gas, mechanical or plumbing system, has to apply to the building official first.

The building official reviews plans against the adopted codes and other ordinances before issuing the permit, and can require a Georgia-registered architect or engineer's stamped drawings for larger commercial buildings, though single-family dwellings are exempt from that design-professional requirement regardless of size. An application is deemed abandoned six months after filing if no permit issues, though the building official can grant one or more 90-day extensions for good cause. Once issued, a permit itself expires six months after the last passed inspection, or six months after issuance if no inspection was ever approved, subject to a similar extension.

Section 18-37 requires the permit to be displayed on the premises and lets police officers check it during a job. Retaining walls over four feet in height, or any wall that supports soil bearing a structure, need their own permit under Section 18-40, and a stamped engineer's design where the backfill slope exceeds one foot of rise per three feet of run.

Violations & Fines

Section 18-32 makes it unlawful to build without complying strictly with the adopted construction codes, and Section 18-60 charges each day of unpermitted construction as a separate offense, punishable under the general penalty in Section 1-11. Section 18-56(g)(2) adds a specific surcharge for starting work before a permit issues: a penalty equal to 100 percent of the usual permit fee on top of the fee itself.

Frequently Asked Questions

Do I need a permit to build a shed in Acworth?
It depends on what it does. Section 18-40 exempts detached utility structures of 120 square feet or less from some retaining-wall permit triggers, but any structure regulated under the adopted construction codes generally, including most sheds tied to electrical or over a certain size, needs a permit under Section 18-56 before work begins; check with the building official first.
What happens if I start construction in Acworth before getting a permit?
You're charged the normal permit fee plus a penalty equal to 100 percent of that fee under Section 18-56(g)(2), on top of exposure to the general Code penalty in Section 1-11 for building without complying with the construction codes, and each day the unpermitted work continues counts as a separate offense under Section 18-60.
How long is an Acworth building permit valid once issued?
Six months from the last passed inspection, or six months from the issue date if no inspection was ever approved, per Section 18-56(f)(1). The building official can grant a six-month extension for due cause if the permit holder asks in writing before it expires, sometimes for an additional fee.

Sources & Official References

Other rules in Acworth

All Acworth rules

Compare Acworth to another location·View the Georgia building safety overview

Get notified when Building Permits in Acworth, GA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.