Acworth, GA Building Safety: Plumbing Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Adopted code
Georgia State Minimum Standard Plumbing Code
Sewer/septic precondition
Required before any building permit, § 18-36
Permitting department
City of Acworth Building Department
Fee
Set in city fee schedule, § 18-35
Max fine
$1,000, six months jail, or both

Summary

Acworth enforces the Georgia State Minimum Standard Plumbing Code on every plumbing installation, alteration, repair or replacement tied to a water or sewer line inside city limits. The Building Department issues the permit and sets the fee, and every builder must also secure a sewer tap or county septic permit before the city will issue a building permit at all.

(3)Georgia State Minimum Standard Fire Code(4)Georgia State Minimum Standard Plumbing Code(5)Georgia State Minimum Standard Mechanical Code ... Associated fees pertaining to the adopted construction codes listed section 18-31 shall include, but are not limited to: residential and commercial building, duct and envelope tightness verification, mechanical, heating, venting and air conditioning, plumbing, electrical, gas, energy, retaining walls, swimming pools, signs, copies of records, and penalties, as adopted by the mayor and board. ... All builders shall obtain a sewer tap or a county septic tank permit before issuance of a building permit by the city. ... 4.Plumbing: The provisions of the Georgia State Minimum Standard Plumbing Code, as adopted and amended by the Georgia Department of Community Affairs, shall apply to every plumbing installation, including alteration, repairs, replacement, equipment, appliances, fixtures, fittings and appurtenances, and when connected to a water or sewerage system.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 27).

Full Breakdown

" Section 18-32 makes it unlawful for any person to undertake construction, commercial or residential, "unless such construction is accomplished in strict compliance with the various construction codes adopted by this article," plumbing among them. " Section 18-36 adds a plumbing-specific precondition many cities skip: every builder must obtain a sewer tap or county septic tank permit before the city will issue a building permit at all, tying the plumbing connection into Cobb County's sewer or septic system directly into the city's permitting sequence. Section 18-35 folds the plumbing permit into the same fee schedule that covers building, electrical, mechanical, gas and energy permits, with the dollar amount fixed by the mayor and board of aldermen and kept on file with the city clerk.

Section 18-33 designates a city official as responsible for enforcing the adopted codes, and that official's Building Department performs the inspections required before plumbing work can be covered or connected to service.

Violations & Fines

Section 18-34 subjects any violation of the adopted construction codes, unpermitted plumbing included, to the city's general penalty in section 1-11: up to a $1,000.00 fine, up to six months in jail, up to 60 days of public works labor, or a combination. Section 1-11 treats each day the violation continues as a separate offense, and section 18-36's sewer-tap precondition means the city can withhold a building permit entirely until the plumbing connection is confirmed.

Frequently Asked Questions

Do I need a permit for plumbing work in Acworth?
Yes. Section 18-31 adopts the Georgia State Minimum Standard Plumbing Code for the city, and section 18-32 makes it unlawful to build, including plumbing installations and alterations, without complying with the adopted code and obtaining the required permit from the Building Department.
Does Acworth require a sewer tap before building?
Yes. Section 18-36 requires every builder to obtain a sewer tap or a county septic tank permit before the city will issue a building permit, tying the plumbing connection directly into the city's permitting sequence.
What plumbing work does the adopted code cover?
Section 18-53 says the Georgia State Minimum Standard Plumbing Code applies to every plumbing installation, including alteration, repairs, replacement of equipment, appliances, fixtures and fittings, whenever the work connects to a water or sewer system.
What happens if I skip the plumbing permit?
Section 18-34 makes the violation punishable under the city's general penalty, section 1-11: up to a $1,000 fine, up to six months in jail, or up to 60 days of public works labor, with each day of the violation counted separately.

Sources & Official References

Other rules in Acworth

All Acworth rules

Compare Acworth to another location·View the Georgia building safety overview

Get notified when Plumbing Permits in Acworth, GA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.