Permit required for
structural, plumbing, electrical, HVAC work
Issuing office
Building Commissioner
Work must start
within 120 days of issuance
Absolute expiration
2 years from issuance
Maximum total extension
1 additional year
Unpermitted work penalty
fee tripled, § 151.26(C)

Summary

LaPorte County requires a building permit under § 151.20 before any construction or alteration that adds or changes support members, or installs new plumbing, permanent heating or air conditioning, electrical wiring, water heaters, or gas or wood-burning fireplaces and stoves in the unincorporated county. The Building Commissioner's office issues every permit and collects the fee.

These county ordinances apply to unincorporated areas of LaPorte County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

(A) A permit shall be obtained before beginning any construction or alterations of any building in the county which requires a change or addition to any support members or the installation of new plumbing, heating, air conditioning, stationary or permanent, electrical wiring, installation of new water heaters, and fireplaces and stoves, whether gas or wood burning. ... (C)(1) All permits issued by the Office of the Building Commissioner shall expire if work has not begun within 120 days of the issuance of the permit. All permits will expire within two years from the date of issuance.

Full Breakdown

Permits are issued by the Building Commissioner's office under § 151.20(B), and every permit expires if work has not begun within 120 days of issuance, with an absolute two-year expiration from the issue date per § 151.20(C)(1). The Commissioner may extend the start deadline by up to 90 additional days for just cause, and may push the completion date up to 180 additional days at a time if the applicant shows reasonable cause and a realistic finish plan, but § 151.20(C)(3) caps all extensions at one additional year total; after that a brand-new permit is required.

Applications must include a plat or sketch showing lot boundaries, floor plans, and estimated construction cost under § 151.21(A)(1), and no local permit issues until the state Fire and Building Code Services Department's building permit release is on file, per § 151.21(A)(2). Contractors and subcontractors doing the work must already be registered with the county, though § 151.21(A)(4) allows a homeowner to do his or her own work as long as required inspections happen. Before issuing a permit, the Commissioner's office also confirms zoning compliance, verifies the applicant holds a valid septic permit, and for floodplain sites checks that construction materials and anchoring will resist flood damage under § 151.21(B).

Fee schedules for specific project types, from single-family homes up to $0.50 per square foot to detached garages and pole barns, are set separately at §§ 151.26 and 151.27.

Violations & Fines

Doing work without a required permit risks more than a stop-work order: § 151.26(C) triples the ordinary permit fee as a penalty once work has proceeded unlawfully without one, and that tripled fee does not excuse the person from any other penalty. Under § 151.23(E), the Building Commissioner can issue a written stop order for work violating the chapter, and anyone who keeps working after being served, including the contractor, subcontractor, or property owner, faces the fines and remedies at §§ 150.15 through 150.21.

Frequently Asked Questions

What triggers the LaPorte County building permit requirement?
Any construction or alteration that adds or changes a support member, or installs new plumbing, permanent heating or air conditioning, electrical wiring, a water heater, or a gas or wood-burning fireplace or stove, needs a permit under § 151.20(A) before work begins in the unincorporated county. The Building Commissioner's office issues the permit and collects the fee.
How long is a LaPorte County building permit good for?
Work must start within 120 days of issuance or the permit lapses, and every permit expires outright two years from its issue date under § 151.20(C)(1). The Commissioner can grant a 90-day extension to begin work and further 180-day extensions to finish, but total extensions can never exceed one additional year under § 151.20(C)(3).
Can a homeowner do the work without hiring a registered contractor?
Yes. Section 151.21(A)(4) allows a homeowner to perform his or her own work on the property, but the required inspections under § 151.23 still have to happen, and any contractor or subcontractor who is hired must already be registered with the county.

Sources & Official References

Other rules in LaPorte County

All LaPorte County rules

Compare LaPorte County to another location·View the Indiana building safety overview

Get notified when Building Permits in LaPorte County, IN changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.