Loveland, CO Building Safety: Building Permits (2026)
Key Facts
- Roof repair permit-free
- Up to 100 sq ft, like-for-like
- Roof permit required
- Over 100 sq ft up to 49% of roof
- Full tear-off
- Over 49% needs non-like-for-like permit
- Permit procurement window
- 90 days after application processed
- Permit expiration
- 180 days if work not started
- Government exemption
- US, Colorado, Larimer County projects
Summary
Loveland requires a building permit for construction, alteration, or repair work under Loveland Municipal Code § 15.08.020, which amends the adopted International Building Code's exempt-work list. Most repair and remodel work needs a permit unless it falls on a short exemption list; a partial roof repair under 100 square feet is exempt, but anything larger up to 49 percent of the roof needs a like-for-like roof permit, and a full tear-off needs a non-like-for-like permit.
14. A partial roof replacement/repair that does not exceed one square (100 sq. ft.) can be repaired like for like without a permit. A partial roof replacement/repair that exceeds one square but does not exceed forty-nine percent (49%) of the total roof will require a roof permit constituting a like for like replacement/repair. A roof replacement/repair exceeding forty-nine (49%) of the total roof (a "full tear off") requires a permit that may not constitute a like for like replacement/repair.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 13).
Full Breakdown
020(D). 2 keeps most of the IBC's baseline exemptions, deletes the oil-derrick exemption, and narrows the sidewalk-and-driveway exemption to structures no more than 30 inches above grade that are not over a basement. It adds a Loveland-specific roofing threshold: a partial roof replacement or repair of no more than one square, 100 square feet, can be done like-for-like without any permit; work beyond that square but at or under 49 percent of the total roof needs a roof permit for like-for-like replacement; and any job exceeding 49 percent of the roof, a "full tear off," needs a permit and is not restricted to like-for-like materials, with asphalt shingles required to meet Class 4 impact-resistant UL 2218 test 2 standards.
The same amendment exempts structures or work on property owned by the United States, the State of Colorado, or Larimer County. 190 governs it: it must be procured within 90 days of the Building Official's office processing the application, becomes invalid if work does not start within 180 days of issuance or is stopped for 180 days, and the Building Official can grant extensions of up to 180 days at a time for justified cause. No permit issues while the applicant owes the city fees on any prior permit.
Violations & Fines
Building without a required permit, or violating any condition of one, is unlawful under § 15.04.230 and carries the general municipal penalty set at § 1.12.010, which supersedes any lesser penalty written into the adopted IBC. The Building Official can also issue a stop work order, and a permit issued on inaccurate or incomplete information can be suspended or revoked outright under § 15.04.190(F). A denied or revoked permit can be appealed to the Construction Advisory Board within 15 days.
Frequently Asked Questions
Can I patch my roof in Loveland without a permit?
How long do I have to start work after getting a Loveland building permit?
Does the city need a permit for its own construction projects?
Sources & Official References
Other rules in Loveland
Compare Loveland to another location·View the Colorado building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Building Permits in Nearby Cities
How other cities in Larimer County handle building permits.