Skip to main content
CityRuleLookup

Jefferson Parish, LA Building Safety: Building Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permit trigger
Construct, enlarge, alter, repair, move, demolish, or change occupancy
Enforcing office
Code Official, Jefferson Parish
Key exemptions
Interior painting, small roof/window repairs, playhouses
Violation fee
$50 minimum, $1,000 maximum
Industrial property fee
Up to $25,000 first, $50,000 repeat
Applies in
Unincorporated parish, including Metairie and Terrytown

Summary

Jefferson Parish requires a building permit before anyone constructs, enlarges, alters, repairs, moves, demolishes or changes the occupancy of a building. A specific list of minor work is exempt, but starting anything else without a permit is a violation with its own fee schedule.

These county ordinances apply to unincorporated areas of Jefferson Parish. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

Any owner, person, firm corporation, or contractor who desires to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure, shall first make application for a building permit to the Code Official except as listed in section 8-1-103.4, work not requiring a building permit. All required permit(s) shall be obtained before the commencement of such work. Any party who shall perform such work, or who causes any such work to be done prior to obtaining the required permit or prior to making the necessary filing shall be held in violation of this chapter and subject to the penalties stated herein.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 20 Update 2).

Full Breakdown

Sec. 1(a) of the parish's Building and Related Construction Code sets the trigger: any owner, contractor or firm that wants to construct, enlarge, alter, repair, move, demolish or change the occupancy of a building or structure must first apply to the Code Official for a building permit, and the permit must be obtained before work starts. The same section carves out an exception list in Sec. 4, which the parish frames as work that does not need a permit unless the Code Official judges it hazardous or complex: interior painting and finish work such as tiling or carpeting on one- and two-family homes, exterior painting, like-for-like window and door replacement that fits an existing rough opening, roof covering or gutter work affecting less than 50 percent of the roof, playhouses and playground equipment, construction shacks and dumpsters during active building, pile load tests and soil borings, and fence board replacement that does not move or add posts.

Paving of private walkways and driveways is also exempt, though sidewalks, curb cuts and paving in the parish right-of-way still need a Public Works permit under chapter 29. Roof replacements covering more than half the roof area on a one- or two-family dwelling require their own application under Sec. 1(c), with photo or video documentation geotagged and uploaded to the parish permitting system, or a FORTIFIED designation certificate in lieu of photos. A permit issued under this chapter only authorizes the specific work shown on the approved plans; any construction not clearly shown on those plans is unauthorized and must stop until a separate permit is obtained, per Sec.

2. This applies throughout unincorporated Jefferson Parish, covering Metairie and Terrytown, which rely on the parish rather than a city hall; Kenner, Gretna, Harahan and Westwego administer their own building permits.

Violations & Fines

Commencing permitted work before the permit is issued triggers a violation fee under Sec. 8-1-104.3 equal to the permit fee, with a $50.00 floor and a $1,000.00 ceiling. On industrially zoned or used property the maximum rises to $25,000.00 for a first violation and $50,000.00 for a second or later violation on the same property within five years. The parish will not issue the permit until the violation fee is paid, and payment does not excuse the owner from meeting the chapter's other requirements.

Frequently Asked Questions

What work requires a building permit in Jefferson Parish?
Sec. 8-1-103.1(a) requires a permit before anyone constructs, enlarges, alters, repairs, moves, demolishes or changes the occupancy of a building or structure. The permit must be obtained before work begins, and doing the work first is itself a violation under the same section.
Is repainting my house or replacing a window exempt?
Yes. Sec. 8-1-103.4 exempts interior and exterior painting and replacement windows or doors on one- and two-family homes, as long as the new window or door fits the existing rough opening and does not reduce its size.
Do I need a permit to replace my roof?
Only if the replaced area exceeds 50 percent of the total roof, per Sec. 8-1-103.1(c). That application requires geotagged photo or video documentation of code compliance uploaded to the parish permitting system, or a FORTIFIED evaluator certificate instead.
What is the penalty for building without a permit in Jefferson Parish?
Sec. 8-1-104.3 sets a violation fee equal to the permit fee, ranging from a $50 minimum to a $1,000 maximum, which must be paid before the permit can be issued. Industrially zoned property faces fees up to $25,000 for a first violation and $50,000 for a repeat violation within five years.

Sources & Official References

Other rules in Jefferson Parish

All Jefferson Parish rules

Compare Jefferson Parish to another location·View the Louisiana building safety overview

Get notified when Building Permits in Jefferson Parish, LA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.