Skowhegan, ME Building Safety: Building Permits (2026)
Key Facts
- Permit authority
- Building Official, as per the MUBEC
- Application
- Completed application with construction documents and valuation
- Fee
- Non-refundable application fee before issuance
- Start without permit
- Permit fees otherwise set are doubled
- After issuance
- Modifications need a revised permit before work
- Ordinance effective
- July 1, 2012
Summary
In the Town of Skowhegan, Maine, building permits are required as per the Maine Uniform Building and Energy Code and expire as that code specifies. The Building Official issues no permit until a completed application is filed and fees are paid, and work begun without a permit has its fees doubled.
5. Building Permits. Building permits are required as per the MUBEC and shall expire as specified therein. No building permit shall be issued by the Building Official until such time that the applicant submits a completed building permit application. Such application shall: ... 9. Fees. ... Prior to issuance of a Permit, the applicant shall be required to pay a non-refundable application fee. No building permit shall be issued until all fees due have been paid. ... 15. After the Fact Permits. In the event that any person is found to have begun work prior to obtaining a permit as required, the permit fees otherwise set forth in the schedule of fees shall be doubled.
Full Breakdown
Building permits in the Town of Skowhegan are governed by Section 5 of the Maine Uniform Building and Energy Code Administrative Ordinance, adopted at Town Meeting on June 11, 2012 and effective July 1, 2012. The ordinance does not list its own dollar thresholds for when a permit is needed: it states that building permits are required as per the MUBEC and expire as specified there. The Building Official receives permit applications, examines construction documents and issues permits for the erection and alterations of buildings and structures.
The Building Official issues no permit until the applicant submits a completed building permit application. The application must identify and describe the work, describe the land by legal description, street address or similar description, indicate the use and occupancy intended, be accompanied by construction documents and other information required by the MUBEC, state the valuation of the proposed work, and be signed by the applicant or the applicant's authorized agent. The Building Official can also require such other data and information as needed. For structures covered by the International Building Code, the application must include certification of a contractual arrangement between a Third-Party Inspector and the building owner, and a copy of all required State of Maine Fire Marshal's building permits must be included.
Under Section 6, the Building Official examines applications and either issues the permit or sends written notice of refusal stating the reasons. All other permits required for the proposal must be obtained before the building permit is issued, and Section 4(h) has the Building Official refer permits requiring subdivision, shoreland zoning or floodplain review to the Planning Board.
Before a permit is issued the applicant pays a non-refundable application fee, and fees are set by the Board of Selectmen in a published schedule. Under Section 10, any modification after issuance requires a revised permit application and a revised permit before work begins. Separately, the Skowhegan Building Safety Ordinance, Section (11)B, requires anyone constructing or placing a new principal or accessory structure to notify the Code Enforcement Officer on forms provided by the Town.
Violations & Fines
Section 15 provides that anyone found to have begun work before obtaining a required permit has the permit fees in the schedule of fees doubled. Section 12 makes it unlawful to erect, construct, alter, extend, repair, move, remove, demolish or occupy a regulated building in violation of the MUBEC, and Section 13 sets civil penalties under 30-A M.R.S.A. § 4452, with each day after notification a separate violation.
Frequently Asked Questions
When is a building permit required in Skowhegan?
What goes in a Skowhegan building permit application?
What happens if I start work before getting a permit?
Do I need other approvals before the building permit?
Sources & Official References
Other rules in Skowhegan
Compare Skowhegan to another location·View the Maine building safety overview