Key Facts
- Permit issued by
- Skowhegan Road Commissioner, within five working days
- Permit fee, Section 2.2.1 access
- None charged
- Entrance width
- At least 20 feet at the curb line
- Driveway width
- At least 12 feet, at most 42 feet
- Surface
- All-weather surface for at least 50 feet from the road
- Distance from intersection
- 50 feet unless Road Commissioner approves
- Fine for no access permit
- Limited to twenty-five dollars
Summary
In the Town of Skowhegan, Maine, a new or upgraded driveway onto a public way needs a permit from the Road Commissioner, issued within five working days. Driveway entrances must be at least 20 feet wide at the curb line, the driveway between 12 and 42 feet wide, with a suitable all-weather surface for at least 50 feet from the public road.
2.2.1 An access proposed to service an individual property, residence, or business which is not a development subject to review under section 2.2.2 must receive a permit from the Skowhegan Road Commissioner prior to commencement of construction. A permit shall be issued upon determination that the proposed access meets the standards in section 2.3 of this ordinance. A permit shall be issued within five (5) working days of application. ... 2.3.2.2 Driveway entrances shall be no less than twenty (20) feet in width at the curb line or edge of shoulder. The driveway itself shall be no less than twelve feet (12’) nor more than forty-two (42) feet in width, measured before it flares into the road. ... 2.3.2. ... 4 Access points shall be surfaced with a suitable all-weather surface resistant to erosion for a distance of at least fifty (50) feet from the public road. ... 2.3.2.6 No driveway shall be built within fifty (50) feet of the intersection of two (2) streets as measured along the near edge of pavement of the streets, except upon approval by the Road Commissioner.
Full Breakdown
The Road and Entrance Design Standards Ordinance (Chapter 38) was adopted February 14, 2012 and amended June 10, 2013. Section 2.1 says no new or upgraded driveway, entrance, or public or private road, street or other way can access a public way in the Town without a permit. Section 2.2.1 sends an individual property, residence or business to the Skowhegan Road Commissioner before construction begins; the permit issues once the access meets the Section 2.3 standards, within five working days of application. Section 1.9 adds that no permit fee is charged for access permits under Section 2.2.1. Developments under the Subdivision or Site Review Ordinance are presumed permitted on approval, and an access permitted by Maine DOT needs no separate Town permit.
Section 2.3.2.2 sets driveway entrances at no less than 20 feet wide at the curb line or edge of shoulder, with the driveway itself no less than 12 feet nor more than 42 feet wide, measured before it flares into the road. Section 2.3.2.4 requires a suitable all-weather surface resistant to erosion for at least 50 feet from the public road, and paving, if provided, must be joined and blended with the street pavement. Section 2.3.2.3 requires a well-defined edge, with curbing continuing into the driveway for a minimum of five feet where the road is curbed. Section 2.3.2.6 bars a driveway within 50 feet of a street intersection, measured along the near edge of pavement, unless the Road Commissioner approves.
Other limits: sight distance of 250 feet on either side for streets at 25 MPH or less and 350 feet on others; no more than two access points per 100 feet of frontage; safety islands of at least ten feet where two driveways serve one property on the same street; and construction that prevents water, snow, gravel or debris from reaching the public way. The ordinance governs access to public ways and does not set a front-yard parking standard.
Violations & Fines
The Code Enforcement Officer enforces, with technical help from the Road Commissioner, by written notice naming the violation and ordering the action needed to correct it. Section 1.10 provides for fines under Title 30-A M.R.S.A. section 4452, except that the fine for failing to obtain an access permit under Section 2.2.1 is limited to twenty-five dollars. The Selectmen can enter administrative consent agreements to resolve violations and recover fines without court action.
Frequently Asked Questions
Do I need a permit to build a driveway in Skowhegan?
How wide can a Skowhegan driveway be?
Does the driveway have to be paved?
How close to a corner can a driveway go?
What is the penalty for skipping the access permit?
Sources & Official References
Other rules in Skowhegan
Compare Skowhegan to another location·View the Maine parking rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.