Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified October 2026

Key Facts

Residential, Zone AE
Lowest floor at least 1 foot above base flood elevation
Residential, Zone A without data
At least 2 feet above the highest adjacent grade
Utility equipment
Bottom of equipment at least 1 foot above base flood elevation
Proof of elevation
Elevation Certificate by a Professional Land Surveyor
Certificate of Compliance
Issued within 10 working days of review
Substantial improvement
Cost equal to or over 50 percent of market value

Summary

In the Town of Skowhegan, Maine, a new or substantially improved residential structure in Zone AE needs its lowest floor, including the basement, at least one foot above base flood elevation. In Zone A with no base flood data, the floor must be at least two feet above the highest adjacent grade. Utility equipment must also sit one foot above base flood elevation.

F. Utilities - New construction or substantial improvement of any structure (including manufactured homes) located within Zones A and AE, shall have the bottom of all electrical, heating, plumbing, ventilation and air conditioning equipment, permanent fixtures and components, HVAC ductwork and duct systems, and any other utility service equipment, facilities, machinery, or connections servicing a structure, elevated to at least one foot above the base flood elevation. ... H. Residential - New construction or substantial improvement of any residential structure located within: ... shall have the lowest floor (including basement) elevated to at least one foot above the base flood elevation. ... b. in the absence of all data described in Article VIJ.H.2.a., to at least two feet above the highest adjacent grade to the structure.

Full Breakdown

Article VII of the Town of Skowhegan's Floodplain Management Ordinance, enacted June 10, 2024, sets the elevation standards for development in Zones A and AE. Article II defines the base flood as a flood having a one percent chance of being equaled or exceeded in any given year, the 100-year flood.

Residential (Article VII.H): new construction or substantial improvement of a residential structure in Zone AE shall have the lowest floor, including basement, elevated to at least one foot above the base flood elevation. In Zone A the same one foot standard applies where base flood data come from the sources the ordinance names, and in the absence of all that data the lowest floor must be at least two feet above the highest adjacent grade to the structure.

Non-residential (VII.I): in Zone AE the lowest floor goes at least one foot above base flood elevation, or the building is floodproofed to at least one foot above it so that it is watertight below that level, with structural components resisting hydrostatic and hydrodynamic loads and a registered professional engineer or architect certifying the design.

Manufactured homes (VII.J): the lowest floor sits at least one foot above base flood elevation on a permanent foundation. Utilities (VII.F): the bottom of electrical, heating, plumbing, ventilation and air conditioning equipment, ductwork and other service equipment must be elevated to at least one foot above base flood elevation.

Trigger: Article II defines substantial improvement as work whose cost equals or exceeds 50 percent of the market value of the structure before construction starts. Accessory structures in Zones A and AE are exempt from the elevation criteria only if limited to a one-story two car garage with an unfinished interior not used for habitation, located outside the floodway.

Proof: under Article VI.F the Planning Board issues a two part permit for elevated structures. Part I authorizes construction up to the first horizontal floor, then an under-construction Elevation Certificate from a Professional Land Surveyor is reviewed within 72 hours before the Code Enforcement Officer issues Part II.

Violations & Fines

Article XI makes the Code Enforcement Officer responsible for enforcement under 30-A MRSA § 4452 and applies that statute's penalties to any violation. Occupancy of an elevated structure requires a Certificate of Compliance under Article VIII, which depends on an Elevation Certificate and written notice of completion. A building built below the required elevation cannot get that certificate, and the officer can request denial of flood insurance.

Frequently Asked Questions

How high must a new house in a Skowhegan flood zone be built?
In Zone AE, the lowest floor, including the basement, must be elevated to at least one foot above the base flood elevation. In Zone A without base flood data, the lowest floor must be at least two feet above the highest adjacent grade to the structure.
Does the elevation rule apply to a major renovation of an existing home?
Yes, when the work is a substantial improvement. Article II defines that as reconstruction, rehabilitation, addition or other improvement costing 50 percent or more of the structure's market value before the work starts, including structures with substantial damage. Article VII.H then applies the same elevation standard as new construction.
Where does the furnace or electrical panel have to go in a Skowhegan flood zone?
Article VII.F requires the bottom of all electrical, heating, plumbing, ventilation and air conditioning equipment, fixtures, ductwork and any other utility service equipment servicing a structure in Zones A and AE to be elevated to at least one foot above the base flood elevation.
Can a commercial building be floodproofed instead of elevated in Skowhegan?
Yes, in Zone AE. A non-residential structure can be floodproofed to at least one foot above base flood elevation so it is watertight below that level, but a registered professional engineer or architect must certify the design with the permit application and record the floodproofed elevation.
What paperwork proves the elevation was built correctly?
An Elevation Certificate completed by a Professional Land Surveyor. Under Article VI.F it is reviewed within 72 hours at the first floor stage before Part II of the permit issues, and Article VIII requires it again before the Code Enforcement Officer decides on a Certificate of Compliance within 10 working days.

Sources & Official References

Other rules in Skowhegan

All Skowhegan rules

Compare Skowhegan to another location·View the Maine environmental rules overview

Get notified when Flood Elevation Requirements in Skowhegan, ME changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.