Key Facts

Governing ordinance
Ordinance No. 12, effective July 1, 2026
Code adopted
2024 International Building Code and Residential Code
Enforcing agency
Adams County Building Safety Division
Fence exemption
Fences up to 7 feet need no building permit
Appeal deadline
30 days to Board of Building Code Appeals
Maximum fine
$1,000 per violation, per day

Summary

Unincorporated Adams County adopted the 2024 International Building Code by reference through Ordinance No. 12, effective July 1, 2026, so any construction, alteration, repair or occupancy change needs a Building Safety Division permit unless the work is specifically exempted. Section 105.2 lists the exemptions, including short fences, minor roof patches and certain farm buildings, but plumbing, mechanical and electrical work on those same structures still needs its own permit.

City-specific rules exist: Thornton has its own building permits rules that differ from Adams County's county-level regulations. If you live in Thornton, check the city-specific page instead.

105.2 Work exempt from Permit Buildings:

2. Fences, other than swimming pool barriers, not over 42 inches (1067 mm) 7 feet (2134 mm) high.

14. Replacement of asphalt shingles when over the aggregate roof area there is less than one square (100 square feet) of replacement or repair.

15. Pursuant to C.R.S. § 30-28-201(1), as may be amended, buildings or structures used for the sole purpose of providing shelter for agricultural implements, farm products, livestock, or poultry. Nothing herein eliminates the requirements that (i) any such agricultural building or structure must comply with local land use requirements contained in the Adams County Development Standards and Regulations (e.g., setbacks and size limitations), and (ii) any necessary plumbing, mechanical, or electrical permits for the agricultural building or structure must be sought and obtained from the County.

Full Breakdown

Ordinance No. 12, adopted April 21, 2026 and effective July 1, 2026, repealed the county's 2018-edition building codes and adopted the 2024 International Building Code and related I-Codes by reference (Section 1). 2. § 30-28-201(1). The agricultural exemption is narrow: the structure must still meet the setback and size limits in the Adams County Development Standards and Regulations, and any plumbing, mechanical or electrical work inside it needs its own permit from the county regardless of the building-permit exemption. Every other item on the International Building Code's exemption list not rewritten by the county is adopted exactly as printed in the 2024 edition.

A property owner who is turned down for a permit, or who disputes how the code official applied a section, can appeal to the Adams County Board of Building Code Appeals within 30 days of the decision (Section 4).

Violations & Fines

Building without a required permit is a violation of Ordinance No. 12 and is punishable under C.R.S. § 30-28-409: a fine of up to $1,000 per separate violation, with each day the unpermitted work or use continues counted as a separate offense. The Building Safety Division can require unpermitted work to be exposed for inspection or removed before approving any permit for the structure.

Frequently Asked Questions

Do I need a permit to build a shed for livestock in unincorporated Adams County?
It depends on use under Section 105.2. A structure built solely to shelter farm implements, livestock or poultry is exempt from the building permit itself, but it must still meet the Development Standards and Regulations' setback and size rules, and any electrical or plumbing added to it needs its own permit.
How long do I have to appeal a denied building permit?
Thirty days from the date the Building Safety Division's code official issues the decision. Appeals go to the Adams County Board of Building Code Appeals under Section 4 of Ordinance No. 12, which also hears disputes over how the 2024 International Building Code was interpreted or applied to a specific project.
What building code edition does Adams County currently enforce?
The 2024 International Building Code and 2024 International Residential Code, adopted by Ordinance No. 12 effective July 1, 2026, along with the 2023 National Electrical Code. These replaced the county's 2018-edition building codes and 2017 electrical code.
What happens if I build without a permit?
You risk a fine of up to $1,000 for each separate violation under C.R.S. § 30-28-409, and Adams County treats every day the unpermitted work or occupancy continues as its own separate offense, so penalties can add up quickly until the work is legalized or removed.

Sources & Official References

Other rules in Adams County

All Adams County rules

Compare Adams County to another location·View the Colorado building safety overview

Get notified when Building Permits in Adams County, CO changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Permits in Cities Across Adams County