Troy, NY Building Safety: Building Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified October 2026

Key Facts

Permit issuer
Director of Code Enforcement
Exempt work
Painting, decorating, ordinary non-structural repairs
Permit validity
Four months to begin work; one three-month extension
Base fee
$100 minimum up to $1,000 value of work
Fence permit fee
$50, $100 or $150 by linear feet
Appeal window (zoning or local rules)
Six days to the Zoning Board of Appeals

Summary

In the City of Troy, New York, a building permit from the Director of Code Enforcement is required before anyone starts the erection, construction, enlargement, alteration, removal, demolition, conversion or change in the nature of occupancy of any building or structure. Only painting, decorating and ordinary non-structural repairs are exempt.

§ 141-4. Building permit required. No individual, corporation or firm shall start the erection, construction, enlargement, alteration, removal, demolition, conversion or change in the nature of occupancy of any building or structure, or cause the same to be done, without first obtaining a building permit from the Director of Code Enforcement for each such building or structure; except that no building permit shall be required for the performance of painting or decorating or ordinary repairs which are not structural in nature.

Full Breakdown

Section 141-4 of the Troy City Code applies to individuals, corporations and firms alike, and it requires a permit for each building or structure. The one carve-out is painting or decorating or ordinary repairs which are not structural in nature. Everything else on the list needs the permit first, including a change in the nature of occupancy.

The application goes to the Director of Code Enforcement under § 141-5 and can be filed by the owner, lessee, architect, engineer or contractor. It must state the lot dimensions, street and ward location, anticipated use, estimated duration, valuation of the work and the owner's name and address, with a complete set of plans and specifications in duplicate. The plans need a scaled plot plan showing distances from lot lines. The code states that a residence or other building with less than 1,500 square feet of habitable or fully developed space will not require an architect's or engineer's seal. The Director cannot approve plans that fail to comply with Chapter 285, Zoning.

The code sets no day count for the decision: the Director approves or disapproves within a reasonable time under § 141-7, and gives written reasons on request. A permit is valid to begin work for four months, and the Director can grant one three-month extension for good cause and special circumstances.

Fees under § 141-9 start at a $100 minimum up to $1,000 value of work, plus $14 per $1,000 from $1,001 to $10,000, $13 per $1,000 from $10,001 to $100,000, $12 per $1,000 from $100,001 to $1,000,000 and $11 per $1,000 from $1,000,000 up. A fence permit costs $50 up to 100 linear feet, $100 for 101 linear feet and up, and $150 for 201 plus linear feet. A $50 certificate of occupancy fee is collected when the building permit is issued.

A refusal can be appealed. Questions under the Uniform Fire Prevention and Building Code go through state law, while zoning or local building questions go to the Zoning Board of Appeals within six days of the Director's decision.

Violations & Fines

Under § 141-15 the Director of Code Enforcement can revoke a permit issued in error, obtained through a false statement, or not followed, and can order all operations suspended by stop order until it is rescinded in writing. Section 141-17 bars occupying a new or altered building until a certificate of occupancy issues. Chapter 126 also bars processing permit applications for owners with outstanding taxes, fees or violations on city properties.

Frequently Asked Questions

Do I need a permit to paint or repair my house in Troy, NY?
No permit is required for painting or decorating or for ordinary repairs which are not structural in nature. Section 141-4 exempts those two categories only. Alterations, enlargements, conversions, removals and demolitions all need a building permit from the Director of Code Enforcement first.
How much is a building permit in the City of Troy?
The § 141-9 schedule starts at a minimum charge of $100 up to $1,000 value of work, then adds $14 per $1,000 from $1,001 to $10,000, $13 per $1,000 up to $100,000, $12 per $1,000 up to $1,000,000 and $11 per $1,000 from $1,000,000 up. Fences are priced by linear feet instead.
How long does a Troy building permit last?
Under § 141-7 a permit authorizes beginning work for four months after the date of issuance. For good cause and special circumstances the Director of Code Enforcement can make one three-month extension of that date. If a project is unfinished one year after issuance, § 141-9 lets the applicant obtain a renewal permit for a fee.
How do I appeal a denied permit in Troy?
Under § 141-16, an appeal involving zoning or local building regulations goes to the Zoning Board of Appeals within six days from the date of the Director of Code Enforcement's decision. An appeal involving the Uniform Fire Prevention and Building Code is taken under applicable state law, with a copy of the notice filed with the Director.

Sources & Official References

Other rules in Troy

All Troy rules

New York rules heatmap·Compare Troy to another location·View the New York building safety overview

Get notified when Building Permits in Troy, NY changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.