Key Facts

Permit required before
Any construction begins
Issuing official
Building commissioner
Max monetary penalty
$2,500.00 per violation
Occupancy gate
Certificate of occupancy, Sec. 6-57
Governing sections
Sec. 6-54 to 6-57

Summary

Porter County Sec. 6-54 flatly bans construction without a valid permit from the building commissioner obtained before work begins, and Sec. 6-56 conditions issuance on a complete application and a design that meets all applicable building and zoning laws.

These county ordinances apply to unincorporated areas of Porter County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

Construction is prohibited unless in conformity with a valid building permit obtained from the building commissioner prior to commencement of construction. ... The building commissioner shall issue a building permit to a person after the person has submitted a complete application, including any applicable fee, provided that the proposed construction will conform to all applicable building laws, and will not violate any other applicable ordinances or laws.

Full Breakdown

Sec. " Sec. 6-55 spells out what the application must contain: contact information for the applicant, "a clear and understandable copy of detailed plans and specifications drawn to scale," a plot plan showing the structure's location relative to existing property lines, streets, curbs and sidewalks (waived only for work entirely inside an existing structure), and, if state law requires it, a design release issued under IC 22-15-3 by the state building commissioner and state fire marshal. Sec. 6-56 requires the building commissioner to issue the permit once the application is complete, the fee is paid, and the proposed construction conforms to all applicable building laws and will not violate other ordinances; the same section bars a building commissioner, code official, or inspector with a conflict of interest from issuing or overseeing the permit, requiring referral to the department director instead.

Occupancy is separately gated: Sec. " The county can also withhold future permits from an applicant who owes fees, including bounced checks, under Sec. 6-107(a), or from a property that is out of conformance with zoning under Sec. 6-107(b). This building code chapter does not apply to industrialized building systems or mobile structures certified under IC 22-15-4, or to regulated amusement devices, boilers, pressure vessels, or lifting devices, per Sec. 6-22.

Violations & Fines

The building commissioner may revoke a permit under Sec. 6-108 for a false statement on the application, noncompliance with building standards, failure to follow the building ordinance, or use inconsistent with zoning. Building without a required permit or in an unsafe manner can trigger a written stop-work order under Sec. 6-109, and Sec. 6-111 authorizes a monetary penalty of up to $2,500.00 per violation, with the county also able to bring a civil action under Sec. 6-110 (citing IC 36-1-6-4) to restrain continued violations.

Frequently Asked Questions

Do I need a permit before starting construction in Porter County?
Yes. Sec. 6-54 states that "construction is prohibited unless in conformity with a valid building permit obtained from the building commissioner prior to commencement of construction."
What must a Porter County building permit application include?
Sec. 6-55 requires applicant contact information, scaled detailed plans and specifications, a plot plan showing the structure relative to property lines and streets (unless work is entirely inside an existing structure), and any state design release required under IC 22-15-3.
What is the penalty for building without a permit?
Sec. 6-111 allows a fine of up to $2,500.00 per violation, the building commissioner can issue a stop-work order under Sec. 6-109, and the county can pursue a civil action under Sec. 6-110 to restrain the work.

Sources & Official References

Other rules in Porter County

All Porter County rules

Compare Porter County to another location·View the Indiana building safety overview

Get notified when Building Permits in Porter County, IN changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.