Key Facts

Governing section
SLCRO § 1102.080, Art. 80 § 80-8(A)
Adopted code
NEC 2014 (O. No. 27430)
Filing lead time
24 hours before work begins
Enforcing office
Office of Electrical Inspection
Application lapse
6 months without action
Penalty
Up to $1,000 fine, 90 days jail

Summary

St. Louis County adopts the 2014 National Electrical Code and requires a written permit application at the Office of Electrical Inspection at least 24 hours before any electrical or communications installation begins. Emergency work can start with next-day notice, but unpermitted work is a misdemeanor with added no-permit fines.

City-specific rules exist: Florissant has its own electrical permits rules that differ from St. Louis County's county-level regulations. If you live in Florissant, check the city-specific page instead.

(A)Permits Required: No person, firm, corporation, limited liability company or other business entity, institution or organization shall begin any work of installing, erecting or altering material, wiring, fixtures, or other apparatus to be used for generation, transmission or utilization of electricity or communications equipment or on any structures or premises unless and until written application shall have been filed in the Office of Electrical Inspection for a permit to do the work contemplated at least twenty-four (24) hours before such work shall be commenced and the permit obtained. Such application shall bear the date of beginning such work. In the event of emergency, as defined in this code, work may begin upon notification to the Code Official upon condition that written application be filed in said office the next working day. The application shall describe in detail the nature of such work and shall state the location thereof. In the event of a disaster, as defined in this code, no work shall begin on an electrical system unless the Code Official issues the appropriate permit.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 85 | Traffic: Supplement 80).

Full Breakdown

080 adopts NEC Article 80 (Administration) with local jurisdictional substitutions: wherever the Code says "Department of Electrical Inspection" it means the St. Louis County Department of Transportation and Public Works, and "Code Official" means that department's Director or a designee. Under 80-8(A), Permits Required, no person or business may begin installing, erecting, or altering wiring, fixtures, or other apparatus for generating, transmitting, or using electricity or communications equipment until a written application is filed with the Office of Electrical Inspection at least 24 hours before work starts and the permit is obtained; the application must show the intended start date.

In a declared emergency, work may begin on notice to the Code Official if the written application follows the next working day, but in a declared disaster no electrical work may start until the Code Official actually issues the permit. Applications must be made by the licensed installer or an authorized agent, include four or more sets of construction documents (waivable for minor scope work), and for structures over two stories, documents signed and sealed by a registered design professional showing fire-resistance and penetration details.

An application is treated as abandoned six months after filing unless diligently pursued or a permit issued, though the Code Official may grant successive 90-day extensions for reasonable cause, each carrying its own extension fee under Chapter 1100.

Violations & Fines

Under Article 80, § 80-17, violating the Electrical Code, including working without the required license or permit, failing to arrange inspections, or continuing work after a stop-work order, is a misdemeanor punishable by a fine up to $1,000, imprisonment up to 90 days, or both, with each day of continued violation a separate offense. The Code Official can additionally impose a no-permit, no-inspection-request, or lapsed-permit penalty of up to $500 per violation, appealable to the Board of Appeals.

Frequently Asked Questions

How far ahead do I need to file for an electrical permit in St. Louis County?
At least 24 hours before the work is scheduled to begin, per NEC Article 80, § 80-8(A) as adopted by Section 1102.080. The written application goes to the Office of Electrical Inspection and must state the date the work is to start.
Can I start electrical work before the permit is issued if it's an emergency?
Yes, in a defined emergency you may begin work after notifying the Code Official, provided the written application is filed the next working day. If the county has declared a disaster, however, no electrical work may begin until the Code Official actually issues the permit.
What happens if my electrical permit application just sits unfiled?
It is deemed abandoned six months after the filing date unless it has been diligently pursued or a permit issued. The Code Official may grant one or more 90-day extensions for reasonable cause, each requiring payment of an extension fee set in Chapter 1100.
What is the penalty for unpermitted electrical work in the county?
It's a misdemeanor under Article 80, § 80-17, carrying a fine of up to $1,000 and up to 90 days in jail, with each day treated as a separate offense, plus a no-permit penalty of up to $500 that the Code Official can assess separately.

Sources & Official References

Other rules in St. Louis County

All St. Louis County rules

Compare St. Louis County to another location·View the Missouri building safety overview

Get notified when Electrical Permits in St. Louis County, MO changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Electrical Permits in Cities Across St. Louis County