Everett, MA Building Safety: Electrical Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified October 2026

Key Facts

Who must obtain a permit
All persons doing electrical work in the city
Issuing official
Inspector of wires
Permit validity
Thirty (30) days from date of issuance
If work is not in progress at expiration
Permit voided; new application and fee required
Fee exemption
Churches and schools below college grade level
Fee schedule location
On file in the office of the City Clerk

Summary

In the City of Everett, Massachusetts (Middlesex County), Section 4-55 requires all persons doing electrical work in the city to obtain a permit from the inspector of wires before commencing any work. Under Section 4-57, a permit is valid for thirty days only from issuance and is voided if work is not in progress.

All persons doing electrical work in the city shall obtain a permit from the inspector of wires before commencing any work. ... (a) The fee schedule of the Wire Division, determined in accordance with ordinance, shall be paid and is on file in the office of the City Clerk. (b) Churches and schools below college grade level will be exempt from payment of the fee provided for under this section. ... Permits issued under this division are valid for a period of thirty (30) days only from date of issuance. If work is not in progress at expiration date, permits will be voided. A new application and fee will be required. The inspector of wire must be notified by the permittee upon completion of all work. In the case of new homes, notification must be given when fixtures and devices are installed.

Full Breakdown

Division 2 of Chapter 4 in the Revised Ordinances of the City of Everett, Massachusetts, creates the Inspector of Wires and sets the electrical permit rules. Section 4-55, Electrical Work Permit, Required, says all persons doing electrical work in the city shall obtain a permit from the inspector of wires before commencing any work. The rule is addressed to all persons, not only to licensed contractors, and the permit comes first.

Section 4-56 deals with fees. Under subsection (a), the fee schedule of the Wire Division, determined in accordance with ordinance, shall be paid and is on file in the office of the City Clerk. The dollar amounts are not printed in the ordinance text, so the City Clerk's file is where the rate is read. Subsection (b) exempts churches and schools below college grade level from payment of the fee.

Section 4-57 sets the permit's life. Permits issued under the division are valid for a period of thirty (30) days only from date of issuance. If work is not in progress at the expiration date, the permit is voided, and a new application and fee are required. The permittee must notify the inspector of wire upon completion of all work. For new homes, notification must be given when fixtures and devices are installed, so the inspector can check that stage.

The office behind these rules is created by Section 4-51, which provides for a wire inspector appointed by the building inspector under General Laws chapter 166, section 32. Section 4-52 requires the wire inspector to be an electrician licensed under the laws of the Commonwealth, in charge of the wire division within the building department. Section 4-54 gives the inspector of wires access to buildings and places necessary for those duties.

Violations & Fines

A permit that is not used within thirty days is voided under Section 4-57, and the applicant must file a new application and pay the fee again. Starting electrical work in the City of Everett before the inspector of wires issues the permit breaks Section 4-55. Failing to notify the inspector on completion, or at fixture and device installation in new homes, breaks Section 4-57.

Frequently Asked Questions

Do I need a permit for electrical work in Everett, Massachusetts?
Yes. Section 4-55 of the Revised Ordinances says all persons doing electrical work in the city shall obtain a permit from the inspector of wires before commencing any work. The requirement applies to all persons, and the permit has to be in hand before the work starts.
How long is an Everett electrical permit good for?
Section 4-57 says permits are valid for thirty days only from date of issuance. If work is not in progress at the expiration date, the permit is voided and a new application and fee are required. Plan the start date around the 30-day window.
Where do I find the electrical permit fee in Everett?
Section 4-56(a) says the fee schedule of the Wire Division, determined in accordance with ordinance, is on file in the office of the City Clerk. The ordinance text does not print the dollar amounts. Churches and schools below college grade level are exempt from payment of the fee under subsection (b).
Do I have to tell Everett when electrical work is finished?
Yes. Section 4-57 requires the permittee to notify the inspector of wire upon completion of all work. In the case of new homes, the notification must be given when fixtures and devices are installed. The inspector of wires is the official who issued the permit under Section 4-55.

Sources & Official References

Other rules in Everett

All Everett rules

Compare Everett to another location·View the Massachusetts building safety overview

Get notified when Electrical Permits in Everett, MA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Electrical Permits in Nearby Cities

How other cities in this county handle electrical permits.

Cambridge, MA
Some Restrictions