Horry County, SC Building Safety: Electrical Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Minimum permit fee
$100 per power service application
Covers
New service, change of service, water pumps, fences
Reinspection fee after 2 visits
$25 minimum per visit
Failed/unready inspection fee
$100 minimum per visit
Adopted code
National Electrical Code, Section 6-2

Summary

Horry County charges a minimum $100 permit fee for any power service application, new service or change of service, including water pumps and electric fences. Reinspections after two visits cost at least $25 each, rising to $100 when work isn't ready or was faulty.

These county ordinances apply to unincorporated areas of Horry County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

(a)The minimum permit fee for power service applications, new or change of service for any purpose, to include water pumps and electric fences, shall be one hundred dollars ($100.00).(b)The minimum reinspect fee shall not be less than twenty-five dollars ($25.00) per visit after two (2) inspection visits. The minimum reinspect fee shall not be less than one hundred dollars ($100.00) for work not ready for inspection when called, repairs or corrections not made when inspections are called, and condemned work resulting from faulty work.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 88).

Full Breakdown

Section 6-32 of the Horry County Code sets the floor for electrical permitting outside the county's municipalities. Any power service application, whether it's a new electrical service or a change of an existing one, carries a minimum permit fee of $100, and that minimum expressly extends to installations such as water pumps and electric fences, not just houses. The section also prices reinspections: after a contractor has already used two inspection visits, every additional visit costs at least $25. If an inspector arrives and the work isn't ready for inspection, if required repairs or corrections weren't made when the inspection was called, or if the inspector condemns faulty work, the reinspection fee jumps to a minimum of $100 per visit.

These fees sit alongside the county's broader adoption of the National Electrical Code under Section 6-2, which the building inspection department (Section 6-1) enforces for all construction outside Myrtle Beach, North Myrtle Beach, Conway and the county's other municipalities. In fast-growing unincorporated areas like Carolina Forest and Little River, where there is no city hall to permit through, every service upgrade, whether it's a new panel, a well pump, or an electric fence around a pasture, needs this county electrical permit before an electrician energizes the circuit.

Violations & Fines

Working without the required electrical permit, or calling an inspection before the work is actually ready, triggers the escalated reinspection fees under Section 6-32: at least $25 per visit after the first two, or a minimum $100 charge specifically for no-shows, uncorrected repairs, or condemned faulty work. Unpermitted electrical work more broadly falls under the general Code Section 1-8 penalty referenced in the technical-code adoption ordinance.

Frequently Asked Questions

How much does an electrical permit cost in Horry County?
The minimum fee is $100 for any power service application, whether it's brand-new service or a change to existing service. That $100 floor applies even to smaller installations like a water pump or an electric fence, not just full house wiring.
What if the inspector shows up and the work isn't ready?
After your first two inspection visits, Section 6-32 charges at least $25 for every extra visit. If the electrician wasn't ready, didn't make required corrections, or the inspector condemns the work as faulty, the reinspection fee rises to a minimum of $100 per visit.
Does Horry County follow the National Electrical Code?
Yes. Section 6-2 adopts the latest edition of the National Electrical Code for all construction in the unincorporated county outside Myrtle Beach and Conway, and the Section 6-32 permit and reinspection fees fund the county inspectors who enforce it.

Sources & Official References

Other rules in Horry County

All Horry County rules

Compare Horry County to another location·View the South Carolina building safety overview

Get notified when Electrical Permits in Horry County, SC changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.