Skip to main content
CityRuleLookup

Jessamine County, KY Building Safety: Electrical Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified October 2026

Key Facts

Base inspection fee
$70 per requested trip, including turn downs
Duplex and multi-family
$70 first unit rough-in; $50 per additional unit, per trip
Work not exceeding $30,000
$400 flat rate
Work from $30,001 to $250,000
1.25% of total contract
Work at $250,001 and higher
1% of total contract
Commercial and industrial payment
One third at permit, one third before power, balance 30 days before final

Summary

In unincorporated Jessamine County, Kentucky, electrical inspections are billed on a county fee schedule: $70 per trip for rough in, TOP and final inspections on dwellings, barns, garages and pools, and a contract-based fee on larger work. Electrical permits are not issued until the electrical contractor discloses contract costs.

These county ordinances apply to unincorporated areas of Jessamine County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

Electrical inspection fees in the unincorporated areas of county shall be as follows. (A) Rough in, TOP and final: $70. (1) Fees shall apply to single-family dwellings, mobile homes, renovations, service change outs, barns, out buildings, garages, room additions, swimming pools, and temporary construction service. (2) Per requested trip, including turn downs, inspection fees are due when the inspection is made (each trip). (B) Duplex, multi-family dwellings. (1) First unit rough-in: $70 per trip. (2) Second unit and thereafter: $50 per unit, per trip. (3) Per requested trip, including turn downs. (C) Electrical work not exceeding $30,000: $400 flat rate. (D) All other electrical work. (1) $30,001 to $250,000: 1.25% of total contract. (2) $250,001 and higher: 1% of total contract. ... (4) Electrical permits will not be issued until the electrical contractor complies with this requirement. ... (d) Certificates of compliance will not be issued until fees are paid in full.

Full Breakdown

Section 150.02 of the Jessamine County Code sets electrical inspection fees for the unincorporated areas of the county. The base fee is $70 for rough in, TOP and final inspections. That rate covers single-family dwellings, mobile homes, renovations, service change outs, barns, out buildings, garages, room additions, swimming pools and temporary construction service. The fee is charged per requested trip, turn downs included, and it is due when the inspection is made, so each trip carries its own charge.

Duplexes and multi-family dwellings are priced differently: $70 per trip for the first unit rough-in, then $50 per unit, per trip, for the second unit and every unit after it.

Larger jobs move to a contract-based schedule. Electrical work not exceeding $30,000 pays a $400 flat rate. Work from $30,001 to $250,000 pays 1.25% of the total contract, and work at $250,001 and higher pays 1%. The electrical contractor must provide copies of all contracts pertaining to electrical costs, along with the total cost of electrical materials and labor provided by others. The fee is calculated on the total cost of the electrical system, including emergency power equipment, fire alarm systems, and all data, communication and alarm systems. A separate fee is calculated for each contract, and the fees for dwellings and the other inspections listed in the section are figured per 200 amps of service.

Payment timing is spelled out for commercial and industrial inspections: one third of the inspection fee is due when the permit is issued, one third before the power is turned on, and the balance 30 days prior to final inspection. Electrical permits will not be issued until the electrical contractor complies with the contract-disclosure requirement, and certificates of compliance will not be issued until fees are paid in full. The section carries the history note Ord. passed 4-2-2019.

The schedule applies in unincorporated Jessamine County. Nicholasville and Wilmore have their own codes and their own fees.

Violations & Fines

Section 150.02 prints no fine or jail term of its own. The enforcement tools written into the text are administrative: the electrical permit is not issued until the contractor supplies the contract and cost figures, and the certificate of compliance is withheld until inspection fees are paid in full. On commercial and industrial jobs, the second third of the fee is due before the power is turned on.

Frequently Asked Questions

How much does an electrical inspection cost in unincorporated Jessamine County?
Section 150.02 sets $70 for rough in, TOP and final inspections on single-family dwellings, mobile homes, barns, garages, room additions and swimming pools, charged per requested trip, turn downs included. Duplexes and multi-family dwellings pay $70 per trip for the first unit and $50 per unit, per trip, after that.
When is the inspection fee due on a commercial or industrial job?
The fee is paid in three parts. One third is due when the permit is issued, one third is due before the power is turned on, and the balance is due 30 days prior to final inspection. Certificates of compliance are not issued until the fees are paid in full.
What must the electrical contractor hand over before a permit is issued?
The contractor must provide copies of all contracts pertaining to electrical costs and the total costs of electrical materials and labor provided by others. Electrical permits will not be issued until the contractor complies. A separate fee is calculated for each contract.
Does this fee schedule apply inside Nicholasville or Wilmore?
No. Section 150.02 states that it sets fees in the unincorporated areas of the county. Nicholasville and Wilmore are separate cities with their own codes, so a project inside either city follows that city's rules and fees, not the Jessamine County Code schedule.

Sources & Official References

Other rules in Jessamine County

All Jessamine County rules

Compare Jessamine County to another location·View the Kentucky building safety overview

Get notified when Electrical Permits in Jessamine County, KY changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.