Key Facts
- Adopted code
- National Electrical Code, Sec. 6-25(1)e
- Permit rule
- One permit covers full project, Sec. 6-54
- Contractor requirement
- State qualification certificate, Sec. 6-55
- Max penalty
- 30 days jail or $100.00 fine, Sec. 6-193
- Appeals body
- Building codes board of adjustments and appeals
Summary
Unincorporated Kershaw County adopts the National Electrical Code by reference under County Code Sec. 6-25(1)e and requires a permit and a state-issued qualification certificate before electrical work begins.
There is hereby adopted by reference for the purpose of establishing rules and regulations for the construction, alteration, removal, relocation, demolition, equipment, use and occupancy, location and maintenance of buildings, structures and premises, the current edition of the following codes, including permits, save and except such portions as are hereinafter deleted, modified or amended, of which copies of each are filed in the office of the building official/inspector and the (same are) hereby adopted and incorporated as fully as if set out at length herein with all appendices thereto, unless otherwise specified by the county council. ... e.The National Electrical Code.
Full Breakdown
Section 6-25(1)e adopts the National Electrical Code by reference, along with the International Residential and Building Codes and all future revisions by the S.C. Building Code Council, for the construction, alteration, use, and maintenance of buildings and structures in the county. Section 6-25(2) adds that electric companies serving the county may impose their own specific requirements, which apply on top of the adopted code. Section 6-54 requires the owner or responsible contractor to obtain one permit covering all work needed to complete a project, and Sec.
6-55 bars issuance of an electrical permit unless the contractor presents a certificate of qualification issued by the state municipal association or is otherwise licensed or certified by the state; the county accepts a contractor's license issued by any municipality or county in South Carolina. The county's building codes board of adjustments and appeals, a five-member board that includes an electrical contractor or engineer under Sec. 6-86, hears appeals from the building official's decisions after review by the planning and zoning director per Sec. 6-90.
Reinspections triggered by faulty work, uncorrected defects, or work not ready when called carry a fee set by county council under Sec. 6-112, and all reinspection fees must be paid before the final inspection and before the permit to energize the electrical power is issued.
Violations & Fines
Using a permit in violation of Chapter 6 is a misdemeanor under Sec. 6-191, and willfully violating any provision of the chapter is punishable under Sec. 6-193 by up to 30 days' imprisonment or a fine of up to $100.00. Sec. 6-194 makes each day a violation continues after 20 days' notice from the planning and zoning director a separate misdemeanor.
Frequently Asked Questions
Which electrical code applies in unincorporated Kershaw County?
Do I need a licensed electrician to pull an electrical permit?
What happens if my electrical work fails inspection?
Sources & Official References
Other rules in Kershaw County
Compare Kershaw County to another location·View the South Carolina building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.