Little Rock, AR Building Safety: Electrical Permits (2026)
Key Facts
- Permit required
- Before any electrical work begins (Sec. 8-146(a))
- Who applies
- Master electrician or authorized representative
- Rough-in wait
- 48 hours before concealing wiring (Sec. 8-148)
- Surety bond
- $10,000.00 required before permit issues
- No-permit penalty
- 3x the permit fee (Sec. 8-153)
- Appeals
- Construction board of adjustments, 30-day window
Summary
Little Rock requires an electrical permit from the permit and records office before any electrical work begins, and only the master electrician on the job, or an authorized representative, can pull it. Sec. 8-146 lays out who applies and when; related sections require licensing, staged inspections, and a $10,000.00 contractor bond before work starts.
Sec. 8-146. - Permit generally. (a)No person shall install or perform any electrical work without an electrical permit issued by the permit and records office.(b)Electrical permits must be secured by the master electrician or his authorized representative prior to the commencement of such work.(c)Notwithstanding subsection (b) of this section a building contractor shall be permitted to secure electrical permits and to request inspections on temporary power centers for use during construction of one- and two-family dwellings. The permit may be taken and scheduled for inspection the following workday or it may be placed on a special "will call" file to be held until being requested. The actual construction and maintenance of the temporary construction meter shall be done by a licensed electrical contractor. When a reinspection fee is required as a result of an improper installation, it shall be secured by the electrical contractor making the correction.(d)Applications for permits shall give the exact address by street and number, approximate date inspection is desired, the name of the master electrician in charge of the work and a complete description of the extent of the installation.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 83).
Full Breakdown
Sec. 8-146 sets the baseline: no person may install or perform electrical work without a permit issued by the permit and records office (subsection (a)), and the permit must be secured by the master electrician in charge, or an authorized representative, before work starts (subsection (b)). Subsection (c) carves out a narrow exception for building contractors, who may pull permits and request inspections on temporary power centers used during construction of one- and two-family dwellings, with the actual temporary meter work still done by a licensed electrical contractor. Subsection (d) requires the application to list the exact street address, the requested inspection date, the master electrician's name, and a complete description of the work.
Sec. 8-147 limits who can hold that permit: only persons licensed under the electrical article, or an employer whose permanent employee is a licensed journeyman electrician, unless the property owner is doing work on their own home and can show they hold a current State of Arkansas Master or Journeyman Electrician's license along with proof of ownership and residency.
Inspections are staged. Under Sec. 8-148, wiring cannot be concealed until the electrical inspector has had 48 hours (excluding weekends and holidays) to inspect it after notice, and every joint must carry an approved connection and pigtail before a job counts as roughed in. Sec. 8-149 requires a final inspection notice before current is used, and Sec. 8-150 makes it unlawful for any utility to energize a new structure without the inspector's clearance. Sec. 8-153 penalizes unpermitted work with a fee three times the original permit cost, and no further permits issue until it's paid. Sec. 8-154 requires a $10,000.00 surety bond to the city before any electrical permit is issued. Appeals of an inspector's decision go to the construction board of adjustments and appeals under Sec. 8-121, following the 30-day written-appeal procedure in Sec. 8-30.1.
Violations & Fines
Working without a permit costs three times the original permit fee, and no new permits are issued until that penalty is paid (Sec. 8-153). Concealing wiring before the mandatory 48-hour inspection window, or energizing a structure without the electrical inspector's clearance, is also a violation (Secs. 8-148, 8-150), punishable under the Code's general penalty in Sec. 1-9: up to $1,000.00, doubled for repeat offenses.
Frequently Asked Questions
Who is allowed to pull an electrical permit in Little Rock?
Can a homeowner get their own electrical permit?
How long before I can cover up new wiring?
What happens if I do electrical work with no permit?
Sources & Official References
Other rules in Little Rock
Compare Little Rock to another location·View the Arkansas building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.