Key Facts

Permit required
Before any electrical work begins (Sec. 8-146(a))
Who applies
Master electrician or authorized representative
Rough-in wait
48 hours before concealing wiring (Sec. 8-148)
Surety bond
$10,000.00 required before permit issues
No-permit penalty
3x the permit fee (Sec. 8-153)
Appeals
Construction board of adjustments, 30-day window

Summary

Little Rock requires an electrical permit from the permit and records office before any electrical work begins, and only the master electrician on the job, or an authorized representative, can pull it. Sec. 8-146 lays out who applies and when; related sections require licensing, staged inspections, and a $10,000.00 contractor bond before work starts.

Sec. 8-146. - Permit generally. (a)No person shall install or perform any electrical work without an electrical permit issued by the permit and records office.(b)Electrical permits must be secured by the master electrician or his authorized representative prior to the commencement of such work.(c)Notwithstanding subsection (b) of this section a building contractor shall be permitted to secure electrical permits and to request inspections on temporary power centers for use during construction of one- and two-family dwellings. The permit may be taken and scheduled for inspection the following workday or it may be placed on a special "will call" file to be held until being requested. The actual construction and maintenance of the temporary construction meter shall be done by a licensed electrical contractor. When a reinspection fee is required as a result of an improper installation, it shall be secured by the electrical contractor making the correction.(d)Applications for permits shall give the exact address by street and number, approximate date inspection is desired, the name of the master electrician in charge of the work and a complete description of the extent of the installation.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 83).

Full Breakdown

Sec. 8-146 sets the baseline: no person may install or perform electrical work without a permit issued by the permit and records office (subsection (a)), and the permit must be secured by the master electrician in charge, or an authorized representative, before work starts (subsection (b)). Subsection (c) carves out a narrow exception for building contractors, who may pull permits and request inspections on temporary power centers used during construction of one- and two-family dwellings, with the actual temporary meter work still done by a licensed electrical contractor. Subsection (d) requires the application to list the exact street address, the requested inspection date, the master electrician's name, and a complete description of the work.

Sec. 8-147 limits who can hold that permit: only persons licensed under the electrical article, or an employer whose permanent employee is a licensed journeyman electrician, unless the property owner is doing work on their own home and can show they hold a current State of Arkansas Master or Journeyman Electrician's license along with proof of ownership and residency.

Inspections are staged. Under Sec. 8-148, wiring cannot be concealed until the electrical inspector has had 48 hours (excluding weekends and holidays) to inspect it after notice, and every joint must carry an approved connection and pigtail before a job counts as roughed in. Sec. 8-149 requires a final inspection notice before current is used, and Sec. 8-150 makes it unlawful for any utility to energize a new structure without the inspector's clearance. Sec. 8-153 penalizes unpermitted work with a fee three times the original permit cost, and no further permits issue until it's paid. Sec. 8-154 requires a $10,000.00 surety bond to the city before any electrical permit is issued. Appeals of an inspector's decision go to the construction board of adjustments and appeals under Sec. 8-121, following the 30-day written-appeal procedure in Sec. 8-30.1.

Violations & Fines

Working without a permit costs three times the original permit fee, and no new permits are issued until that penalty is paid (Sec. 8-153). Concealing wiring before the mandatory 48-hour inspection window, or energizing a structure without the electrical inspector's clearance, is also a violation (Secs. 8-148, 8-150), punishable under the Code's general penalty in Sec. 1-9: up to $1,000.00, doubled for repeat offenses.

Frequently Asked Questions

Who is allowed to pull an electrical permit in Little Rock?
Sec. 8-146(b) requires the master electrician in charge of the job, or their authorized representative, to secure the permit before work starts. Sec. 8-147 further limits eligibility to persons licensed under the city's electrical article, or an employer whose permanent employee is a licensed journeyman electrician, with a separate homeowner exception.
Can a homeowner get their own electrical permit?
Yes. Sec. 8-147(b) allows a property owner to pull a permit for work on their own home if they hold a current State of Arkansas Master or Journeyman Electrician's license and can show they own the home and live in it, or will live in it once the work is complete.
How long before I can cover up new wiring?
Sec. 8-148 requires you to notify the electrical inspector and then wait at least 48 hours, not counting weekends or holidays, before covering new wiring or conduit, unless the inspector shows up sooner and approves the work directly on site.
What happens if I do electrical work with no permit?
Sec. 8-153 charges a penalty fee equal to three times the original permit fee that should have been paid for the work, and the city will not issue that party any further permits until the penalty is paid in full.

Sources & Official References

Other rules in Little Rock

All Little Rock rules

Compare Little Rock to another location·View the Arkansas building safety overview

Get notified when Electrical Permits in Little Rock, AR changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.